RF shielding is a CTTA-driven countermeasure, not a default ICD 705 requirement.
Source
Public text
Tech Spec 3.C.4
"RF protection shall be installed at the direction of the CTTA when a SCIF utilizes electronic processing and does not provide adequate RF attenuation at the inspectable space boundary." Installation follows "either the drawings or Best Practices Guidelines for Architectural Radio Frequency Shielding."
Tech Spec 3.C.3.e
CTTA-recommended countermeasures may be "foil backed GWB or layer of approved Ultra Radiant R-Foil"
ICS 705-1 G.1.a(4)
"When RF shielding is required by Certified TEMPEST Technical Authority (CTTA) evaluation, it should be planned for installation during initial construction," because retrofit costs are significantly higher
Tech Spec 4.H.1
Outside the U.S. and not under Chief of Mission authority: "TEMPEST countermeasures shall be pre-engineered into the construction of the SCIF"
UFC 4-010-05 §3-4.1
References RF shielding per the CTTA's recommendations (TCR)
How a requirement arrives. The CTTA's TEMPEST Countermeasures Review may call for no shielding, foil on selected walls, shielded racks, filtered power only, or a full enclosure. It may state an attenuation level. One practitioner cites a CTTA review that specified "60dB of RF attenuation," with milestone inspections, testing and mock-ups. That's an example, not a standard.
There's no single "SCIF shield." The CTTA's requirement, the attenuation level, the budget and the building set the type. Figures below are vendor or practitioner examples, not requirements.
Type
How it's built
Strengths and weaknesses
Published example claims
Welded steel
Continuous welded steel plate; penetrations welded in
Highest and most durable performance; steel helps with low-frequency magnetic fields; costly and hard to modify
Project-specific; no general figure in our sources
Modular / bolted panel
Prefabricated panels with conductive framing. Universal Shielding: "six sided pre-fabricated modular system," with "26 gauge galvanized steel laminated to both sides" of a wood core
Fast and relocatable; seams depend on correct assembly
Universal Modular (modular SCIFs): "up to 80 decibels (dB)," with shielding adding roughly 15–30% to project cost
Copper foil or screen
Copper sheet, foil or screen
Reflects electric fields well; weak against low-frequency magnetic fields
In Compliance (2022): copper and aluminum foil performance drops above about 1.5 GHz
Architectural foil / foil-backed drywall
ETS-Lindgren: "Shielding foils… applied over contractor-provided drywall"; floor material "a minimum of 7.62 cm (3 in) up on all… walls… 'pan' configuration"
The Tech Spec's "foil backed GWB or… R-Foil" path; very workmanship-sensitive (laps, screws, penetrations)
ETS-Lindgren describes a range of "minimal to maximum attenuation" with no single figure
Conductive paint / coatings
Conductive coatings on substrates
Named as an enclosure method (Wikipedia)
Room-scale performance not established in our sources
Magnetic / ELF shielding
Low-carbon or electrical steel, permalloy
For slowly varying magnetic fields, where Faraday shielding below about 100 kHz is "ineffective" (Wikipedia)
Specialty design
Known weak point of foil systems. In Compliance Magazine notes that screws fastening the outer drywall layer penetrate the foil and create leakage. Foil systems generally can't reach the high-frequency performance of welded or modular steel rooms.
Attenuation (shielding effectiveness) is how much weaker a signal is on one side of the shield than the other, expressed in dB. Every 10 dB is a factor of ten in power, so 100 dB is a 10^10 power ratio. Three rules explain almost every shielding failure.
1. Low-frequency magnetic fields are the hardest. ETS-Lindgren publishes its steel honeycomb vent at "25 dB @ 1 KHz" for magnetic fields, but "120 dB" at higher frequencies. Its brass version is weaker at low frequency. Steel absorbs magnetic fields. Copper mostly reflects electric fields.
2. Holes must be much smaller than the wavelength. Wikipedia: "Any holes… must be significantly smaller than the wavelength." A seam gap, an unsealed conduit or a missing screw can leak like an open window. Higher frequencies have shorter wavelengths, so small gaps matter more as frequency rises.
3. A room is only as good as its worst seam, door or penetration. Holland Shielding: "a single weak point can affect the complete room."
Published component claims (vendor examples, not requirements):
Component
Published claim
ETS-Lindgren DKE double knife-edge door
"130 dB at frequencies up to 10 GHz, 100 dB up to 40 GHz, and 90 dB up to 100 GHz"
ETS-Lindgren steel honeycomb vent, 3/16 in cell
Electric "120 dB @ 100 KHz to 30 MHz"; plane wave "120 dB @ 30 MHz to 1 GHz"; microwave "120 dB @ 1 GHz to 18 GHz"
Premier and ETS-Lindgren power filters
"100 dB" from 14 kHz to 40 GHz
Holland 3.2 mm aluminium honeycomb
80 dB at 100 MHz single layer; 105 dB cross-cell
The CTTA or the specification sets the required level. A 130 dB door does nothing for a room whose sprinkler pipe passes through an unbonded hole.
Rule zero: every conductor, pipe, duct or opening that crosses the boundary is a potential leak. Tech Spec 3.G.1: "All penetrations of perimeter walls shall be kept to a minimum."
The right treatment depends on whether the boundary is a full RF shield or a non-shielded SCIF perimeter where the CTTA has directed specific countermeasures. The logic is often opposite: at a shield you bond metal to make it part of the shield; at a non-shielded perimeter you may break the metal path.
Crossing item
RF-shielded enclosure
Non-shielded SCIF perimeter (only if the CTTA directs)
Power
Filter at the shield; bonded case; gasketed clean-side penetration
Power filters per the CTTA; otherwise normal single-point entry
Low-speed signal, phone, fire alarm, IDS, ACS
Signal-line filters at the shield
Filters, isolation or separation per the CTTA
Ethernet and data
All-dielectric fiber through a waveguide plus media converters (or a CTTA-accepted data filter)
Fiber or separation per the CTTA
Metal conduit, pipe, tray
Welded or 360° bonded at the shield; open pipes sized as waveguides
Dielectric break or grounding (Tech Spec 3.G.2)
HVAC duct
Bonded honeycomb waveguide vent
Acoustic and bar/grille rules; dielectric duct break if the CTTA directs
Sprinkler, water, drain
Engineered pipe waveguide, welded or bonded
Dielectric break or grounding if the CTTA directs
Doors
Knife-edge and finger-stock RF door
"shall meet TEMPEST requirements per CTTA guidance" (3.E.5.g)
Also from Tech Spec Chapter 3.G:
"Utilities servicing areas other than the SCIF shall not transit the SCIF unless mitigated with AO approval" (3.G.3).
"Electrical Utilities should enter the SCIF at a single point" (3.G.4).
Interior distribution on treated walls is surface-mounted, in raceway, or on an added furred wall (3.G.5).
UFC 4-010-05 adds that "All metallic perimeter penetrations present compromising emanations (CE) and pose TEMPEST hazards that must be addressed" per the TEMPEST Countermeasure Review.
Why one entry point. Every separate penetration needs its own bond, gasket, inspection and test point. Grouping them is cheaper, easier to inspect and far easier to test. It's also what the public criteria ask for:
Tech Spec 3.G.4: "Electrical Utilities should enter the SCIF at a single point."
UFC 4-010-05 §3-4.11.1: "Utilities (power and signal) should enter at a single point. Seal all utility penetrations to mitigate acoustic emanations and covert entry."
UFC 4-010-05 §3-4.19: "Cabling must enter the protected area from a single location."
The penetration panel. On a shielded room, the shield vendor typically provides a penetration panel (or entry plate) where these are mounted and bonded together:
Mounted on the panel
Notes
Power-line filters or filter panel
Dirty side outside, clean side inside
Signal-line filters
Phone, fire alarm, IDS, ACS, low-speed control
Fiber waveguide tubes
All-dielectric fiber only
Spare waveguides or capped spares
RF-sealed, and included in the test
Single-point shield ground
Where the design places it
Spare capacity. Tech Spec 3.G.6 allows expansion conduit "filled with acoustic fill and capped." That closure is acoustic. On an RF shield, a spare must also be RF-sealed (for example, a bonded cap or a waveguide sized for future fiber) and tested with the room. This is an inference from shielding practice, so confirm the detail with the shield vendor.
The penetration schedule. Before the shield is fabricated, build a schedule listing every crossing system: power, lighting, fire alarm, sprinkler, HVAC, BMS, plumbing, IDS, ACS, CCTV, PA and mass notification, phone, LAN, RED circuits and fiber. For each, record the treatment, the size and the responsible trade. Then freeze it.
What it looks like. A dielectric union, an insulating flange kit, or a non-conductive flexible duct connector. The product must be listed for the system it's installed in.
Why it's used at a non-shielded SCIF perimeter.
Metal that crosses the perimeter can carry signals picked up inside to the outside. Historical 2-95 warned that a conductive sleeve around lines leaving the inspectable space "can become a fortuitous conductor and could require isolation."
Tech Spec 3.G.2: "Metallic penetrations may require TEMPEST countermeasures, to include dielectric breaks or grounding, when recommended by the CTTA."
For DoD projects, UFC 4-010-05 §3-4.11.2 gives treatments that apply when TEMPEST countermeasures are required: non-conductive duct connections, non-conductive conduit unions, and grounding of conduit, sprinkler pipe and refrigerant lines near the penetration.
The opposite logic at an RF shield. A shield works by being continuous metal, so at a shield you bond every metal penetration so it becomes part of the shield. Any opening is then sized as a waveguide. A dielectric section may also appear outside a shield so building piping doesn't inject currents onto it, but that configuration isn't universal.
Boundary
Metal pipe or conduit strategy
Non-shielded SCIF perimeter (CTTA-directed)
Break it (dielectric) or ground it
RF shield
Bond or weld it to the shield; size openings as waveguides
Code coordination. Non-metallic sections in sprinkler, gas or fire-rated assemblies must be listed for that use and firestopped. Coordinate with the fire protection engineer and the AHJ before ordering.
The physics in one sentence. Below cutoff, the field "decays exponentially along the waveguide axis and the wave is thus evanescent" (Wikipedia). Above cutoff, the tube becomes a pipe for RF.
Two dimensions control performance:
Dimension
Effect
Inside width or diameter
Sets the cutoff frequency. A smaller opening gives a higher cutoff, so it blocks higher frequencies.
Length
Sets how much attenuation you get below cutoff. A longer tube gives more dB.
Where waveguides are used:
Honeycomb vents: hundreds of small cells in parallel pass air.
Pipe waveguides: pass sprinkler water, plumbing or pneumatic lines.
Fiber waveguide tubes: pass optical fiber.
Access ports for filling, draining or inspection, where the shield design includes them.
The one rule you can't break: never put a conductor through a waveguide. A wire, a metallic cable, or a fiber cable with a steel strength member turns the tube into a coaxial line. A coaxial line has no cutoff, so RF passes straight through at every frequency. Historical 2-95 made the same point about metal strength members acting as "fortuitous conductors."
Put through a waveguide
Result
Air, water (engineered), all-dielectric fiber
Works as designed
Copper wire, coax, PoE cable, armored fiber, fiber with steel member, tracer wire, pull string with metal
These are textbook formulas (RF Cafe tabulates the constant 1.841 for the circular TE₁₁ mode). They explain designs and let you sanity-check a submittal. The shield vendor's tested design governs, not a hand calculation.
Shape
Cutoff frequency (air-filled)
Handy form
Circular tube, inside diameter D
fc = 1.841c / (πD) ≈ c / (1.706D)
fc (GHz) ≈ 17.6 / D (cm) ≈ 175.7 / D (mm) ≈ 6.9 / D (in)
Rectangular opening, widest inside dimension a
fc = c / (2a)
fc (GHz) ≈ 150 / a (mm) ≈ 5.9 / a (in)
Filled with a dielectric (e.g., water)
fc ÷ √εr
Water (εr ≈ 80 at low frequency) lowers fc by about 9×
Attenuation below cutoff (derived: α = (2π/λc)·√(1 − (f/fc)²) nepers per unit length, with 1 Np = 8.686 dB). For frequencies well below cutoff (f ≪ fc):
Circular: A ≈ 32 × L/D dB, about 32 dB per diameter of length
Rectangular: A ≈ 27.3 × L/a dB
At f = 0.5 fc, multiply by about 0.87. Attenuation falls to zero as f approaches fc.
Worked example: a 1-inch tube, 5 inches long, air-filled
Step
Calculation
Result
Diameter
1 in = 2.54 cm
D = 2.54 cm
Cutoff
17.6 / 2.54
fc ≈ 6.9 GHz
Length in diameters
5 in / 1 in
L/D = 5
Attenuation well below cutoff
32 × 5
≈ 160 dB (theoretical)
At half of cutoff (≈ 3.5 GHz)
160 × 0.87
≈ 139 dB (theoretical)
Above ≈ 6.9 GHz
Tube propagates
Essentially no protection
Same tube, filled with water: fc ≈ 6.9 / √80 ≈ 0.77 GHz. Frequencies above roughly 770 MHz now propagate through the water column. A design that looked excellent dry offers far less at UHF and microwave frequencies.
Lessons:
The math is ideal. Real limits usually come from the weld or bond where the tube meets the shield.
Rules of thumb for length-to-diameter ratio circulate in industry. Use the vendor's tested dimensions, not a rule of thumb.
The problem. An HVAC duct is a large hole in the shield. A 12-inch-wide rectangular opening has a cutoff near 0.5 GHz (5.9 / 12), so frequencies above that pass through it freely.
The solution. A honeycomb vent splits the opening into many small hexagonal cells. Each cell is a tiny waveguide with a high cutoff frequency, and together they pass enough air. Tech-Etch: hexagonal cells "permit smooth airflow… while also blocking electromagnetic radiation leakage."
Ideal vs measured. A 1/8-inch cell, 1/2 inch deep, has a theoretical cutoff around 47–55 GHz and about 128 dB per ideal cell. Measured panels are far lower. Tech-Etch publishes 40–75 dB for a chem-film 1/8-inch cell, 1/2-inch panel, and 60–105 dB cross-cell, over 100 kHz–10 GHz. Seams, cell joints, frame bonding and finish all cost performance.
Vent example (vendor data, not requirements)
Published attenuation
ETS-Lindgren steel, 3/16 in cell
Magnetic "25 dB @ 1 KHz, 120 dB @ 20kHz"; electric "120 dB @ 100 KHz to 30 MHz"; plane wave "120 dB @ 30 MHz to 1 GHz"; microwave "120 dB @ 1 GHz to 18 GHz"
ETS-Lindgren steel, 1/8 in cell
"100 dB @ 40 GHz"
ETS-Lindgren brass
Magnetic "25 dB @ 1 KHz, 70 dB @ 20kHz"
Holland 3.2 mm aluminium
80 dB at 100 MHz single layer; 105 dB cross-cell
Installation takeaways:
Cross-cell construction uses a "minimal two layers… stepped and rotated 90 degrees" (Holland) for higher performance.
Bond the vent frame by solder, braze, weld, or "RF gasket seals" with "Monel or tin-coated gaskets" (ETS-Lindgren). An unbonded frame leaks around the honeycomb.
Steel beats brass at low-frequency magnetic fields.
The mechanical engineer must account for pressure drop. Honeycomb adds resistance, and acoustic silencers or Z-ducts add more.
Don't cut, drill or screw through the honeycomb, and don't let duct insulation pins pierce it.
Fire protection is mandatory, and a sprinkler main is a metal pipe crossing the shield. The shield-side answer is an engineered pipe waveguide: a metal section welded or bonded to the shield, with a diameter and length chosen so the frequencies of concern are well below cutoff.
Why water changes the math. Water has a very high dielectric constant (εr ≈ 80 at low frequency, a textbook value). Filling a waveguide with it lowers the cutoff frequency by about √80, or roughly 9×.
Same 1-inch tube
Cutoff frequency
Practical meaning
Empty (air)
≈ 6.9 GHz
Good attenuation well below about 7 GHz
Water-filled
≈ 0.77 GHz
RF above roughly 770 MHz can propagate through the water column
A pipe waveguide sized for air can fail badly once the system is charged with water. Sprinkler, domestic water and drain waveguides must be engineered for the fluid they carry. Wet-pipe sprinklers are always full.
Coordination checklist:
Discipline
Question to resolve before fabrication
Fire protection engineer
Listed waveguide fitting? Pipe size and flow? Hydraulic calculations include it?
Shield vendor
Waveguide diameter and length for the fluid; weld or bond detail; included in the test
AHJ
Acceptance of the fitting and any non-metallic sections; firestopping in rated assemblies
AO / CTTA
Treatment at non-shielded perimeter segments; route acceptance
Mechanical / plumbing
Drains, condensate and refrigerant lines get the same review
Routing rules that come from the Tech Spec:
A sprinkler main serving the SCIF may enter. A main feeding other tenant areas "shall not transit the SCIF unless mitigated with AO approval" (3.G.3).
At a non-shielded perimeter, metallic sprinkler pipe may need a dielectric break or grounding when the CTTA recommends it (3.G.2). UFC 4-010-05 §3-4.11.2 gives the DoD grounding treatment.
Why fiber is the preferred data path. Holland Shielding describes the approach as "converting the signal to light and bringing the signal into the shielded room via a fiber optic cable through a waveguide. The fiber optic cable is non-conductive and will not bring in unwanted signals." Historical 2-95 noted that optical fibers "do not conduct or radiate radio frequency interference." In Compliance Magazine (2022) recommends fiber through an inexpensive waveguide over filtering copper data lines.
How it's done:
OUTSIDE | SHIELD | INSIDE
switch -> media converter -> all-dielectric fiber ==[waveguide tube]== fiber -> media converter -> device
(building power) tube welded/bonded to shield (converter on FILTERED power)
The rules:
Rule
Why
No metal in the cable at the penetration
Metal inside a waveguide makes a coax with no cutoff
Use all-dielectric cable: no armor, metallic strength member or tracer wire
2-95 warned that a strength member "can be made of steel or other metal" and called for "no metallic stiffeners or metallic sheath"
If the cable has metal elements, strip them back outside the shield
Per the shield vendor's and CTTA's detail
Media converters inside are powered from filtered circuits
Converter power is still a conductor
Never pass PoE or copper through the wall or waveguide
PoE is copper; it defeats the waveguide
Size the waveguide for the fiber count, plus spares
How an RF door seals. A normal door has gaps at every edge. An RF door closes them with metal-to-metal contact all the way around:
Part
What it does
Knife-edge
A continuous metal blade on the door leaf (or frame)
Finger stock
Rows of springy beryllium-copper contacts that the knife-edge presses into, making continuous electrical contact
Gaskets
Conductive gaskets on covers, panels and some door designs
Frame
Welded or bonded to the shield like any other penetration
ETS-Lindgren's DKE door uses "a durable bronze double knife-edge extrusion" that mates with "four rows of beryllium copper finger-stock… replaceable with standard tools." Its vendor claim is "130 dB at frequencies up to 10 GHz, 100 dB up to 40 GHz, and 90 dB up to 100 GHz," tested per "MIL-STD-285, NSA 65-6/NSA 94-106, ITSG-02/IEEE 299 or EN 50147-1."
SCIF-specific conflicts:
Acoustic vs RF. In Compliance Magazine reports that no single door on the market at the time met both typical SCIF acoustic ratings and top-tier RF performance. Designs use a vestibule, or a separate RF door plus an acoustic door.
Security hardware. Tech Spec 3.E.5.g: "SCIF Perimeter doors shall meet TEMPEST requirements per CTTA guidance." The FF-L-2890 deadbolt, electrified lock, REX, balanced magnetic switch and card reader must all be installed without disturbing the knife-edge or finger stock. Their wiring goes through signal filters or fiber.
Life safety. Egress hardware must work with the RF seal. Coordinate with the AHJ.
Installer rules:
Use only door hardware the RF door manufacturer approves, mounted with its templates.
Never drill the knife-edge, the finger-stock channel or the shielded door skin.
Route door-hardware conductors to the penetration panel, not through the frame.
Hang and adjust per the manufacturer. Historical NSA 94-106 required that "Door hinges shall support the door's weight without sagging… positive closure." That remains good practice.
A shield that passed its acceptance test degrades with use. Doors are the moving part, and they wear first.
RF door maintenance items:
Item
Action
Finger stock
Keep clean and unpainted. Replace bent or broken fingers. ETS-Lindgren designs them to be "replaceable with standard tools."
Knife-edge
Keep clean; don't file, paint or lubricate unless the manufacturer says to
Door alignment
Check for sag and positive closure; adjust per the manufacturer
Gaskets on covers and panels
Replace torn EMI gaskets with factory parts only
Hardware changes
Any new lock, reader or closer is a shield-integrity change. Review it first.
Records
Log inspections and repairs in the facility's O&M file
Seams and joints. Holland Shielding notes that seam conductivity should be "more or less identical to that of the basic material." Seams in modular panels, foil laps and welded joints all need continuous electrical contact.
Corrosion. Dissimilar metals in contact corrode, and corroded joints lose conductivity:
Holland: galvanic corrosion occurs above "0.3 volts in a salty environment, or 0.5 volts in an environment with just water."
Historical NSA 94-106 required "noncorrosive material" and avoiding dissimilar metals.
Humid mechanical spaces, condensate and cleaning chemicals speed up corrosion at gaskets and finger stock.
When to retest. Any change that affects the shield (a new penetration, a door replacement, a panel removed and reinstalled, a seam repair) calls for review and, as directed, a retest. The shield vendor and CTTA define what counts as a change for your facility.
Grounding a shield is not the same as grounding a building. Getting it wrong creates currents on the shield that can defeat it, or a safety hazard, or both.
Single-point shield ground. The shield connects to the building grounding system at one designed point, and is isolated from incidental contact everywhere else. This avoids ground loops that drive currents across the shield surface.
The safety ground is still required.
Holland Shielding: the shield "should be connected to the common ground of the building, only for safety reasons."
Filters need a continuous equipment grounding conductor (ETS-Lindgren).
Don't create a separate, unbonded "clean" earth rod. The electrical engineer and AHJ confirm the electrode system and bonding under the electrical code.
Incidental contacts break single-point grounding:
Offender
Fix
Conduit, strut or hangers touching the shield
Isolate per the shield detail
Duct or pipe hangers anchored through the shield
Hang from the structure outside, or use the vendor's isolated supports
Cable tray resting on the shield
Stand-offs or isolators per the detail
Metal studs of an interior furring wall bearing on the shield
Isolate per the detail
RF bonds are short and wide. Historical 2-95: "Long pigtail and long ground wire shield terminations drastically reduce shielding effectiveness." Cable shields terminate "360 degrees around the cable" (Holland). Use flat braid or direct metal-to-metal contact, not long round wire.
RED/BLACK grounding (equipotential planes, single-point schemes, separated return paths) is designed by the engineer of record and the CTTA, not in the field. See: RED/BLACK, TEMPEST & EMI Filters.
What's tested. A shielding effectiveness test compares signal levels with and without the shield in the path, at the frequencies the specification names. It covers every door, seam, vent, filter and penetration.
IEEE 299 status:
Item
Status in our research
IEEE 299-2006, Standard Method for Measuring the Effectiveness of Electromagnetic Shielding Enclosures
Covers 9 kHz–18 GHz (extendable to 50 Hz and 100 GHz) for enclosures with all dimensions ≥ 2.0 m
Current standing
Listed as Inactive-Reserved (30 Mar 2023)
Revision
Project P299 is in development (PAR approved 13 Feb 2025), proposing extension to 40 GHz
Other methods on current datasheets: MIL-STD-285 (1954), NSA 65-6 and 94-106 (historical), ITSG-02, EN 50147-1 and ASTM E1851-15. Test labs and government customers still reference several of these. Confirm which method and edition your contract cites, the frequencies, and the pass/fail levels, before the shield is designed.
Sequencing rules:
Mock-ups and milestone inspections, if the CTTA or specification requires them (one practitioner describes CTTA-directed mock-ups and testing).
Seam and panel inspection before interior finishes cover the shield.
Final acceptance test only after all penetrations, filters, signal filters, waveguides, vents, doors and door hardware are installed.
Repair and retest any failures.
Any later penetration or modification means review, then retest.
Every screw, anchor, powder-actuated pin or box that pierces the foil or steel is a hole in the shield. In Compliance Magazine notes that even the screws holding the outer drywall layer can penetrate architectural foil and create leakage. Tech Spec 3.G.5 therefore requires utility distribution on the interior of an acoustic- or RF-treated perimeter wall to be "surface mounted, contained in a raceway, or an additional wall… using furring strips as stand-off," so the treated layer is never punctured. The practical consequences are that devices can't be flush-mounted in the shielded wall, TVs and whiteboards can't be anchored straight through it, and hangers can't pass through the shielded ceiling. Installer mounting methods (Z-brackets, surface raceway, furred walls and stand-offs) are covered in a separate part of this module.
[ ] Fire protection: listed sprinkler waveguide and dielectric fittings, engineered for a water-filled pipe; AHJ acceptance.
[ ] Architectural: furred walls or surface raceway so nothing fastens through the shield.
Information handling
[ ] Drawings, penetration schedules, CTTA recommendations and test reports are controlled as sensitive information. They stay off public shares and open bid portals.
A shielded room is built from the outside in and tested last. Out-of-order work is the most expensive shielding mistake, because fixing it means opening finished work and retesting.
Step
Work
Hold point
1
CTTA recommendations and shield design approved; penetration schedule frozen
Verify nothing is roughed through the future shield line
3
Shield erected; seams, laps or welds completed and inspected
Seam inspection before anything covers it
4
Power filters, signal filters, waveguides, honeycomb vents and door frames installed and bonded or welded
Bond and gasket inspection
5
Single-point ground installed; isolation verified
Isolation check before other trades connect
6
Interior raceway, furring and finishes installed without penetrating the shield
"No fasteners through the shield" walk-down
7
Door hardware, low-voltage devices and media converters installed; converters on filtered power
Confirm no copper through the waveguides
8
Shielding effectiveness test (e.g., IEEE 299 or the contract method) after everything above; repair and retest
Passing report
9
Turnover: filter, door and gasket maintenance documentation; AO and CTTA acceptance
O&M and as-builts delivered through controlled channels
10
After occupancy, any penetration change goes through review, then retest
Shield-change log maintained
Notes for the schedule:
ICS 705-1 wants RF shielding "planned for installation during initial construction." Build the test and any retest time into the baseline schedule.
Coordinate the shield test with the AO's other acceptance activities (acoustic testing, IDS certification, TSCM) so a late shield repair doesn't re-open finished areas. See: Construction Security & Build Sequence.
Construction security rules still apply throughout. The shield is part of the SCIF perimeter under construction.
"All utility (power and signal) distribution on the interior of a perimeter wall treated for acoustics or RF shall be surface mounted, contained in a raceway, or an additional wall shall be constructed using furring strips as stand-off from the existing wall assembly."
UFC 4-010-05 §3-4.4.7
Current DoD design criteria (26 May 2023)
Surface mount or furred wall, including "recessed outlet boxes, recessed panels for power, telecommunications, ESS, fire alarm and other systems. Do not mount utilities in a manner that will affect the acoustic or RF shielding performance."
UFC 4-010-05 §3-4.11
Current
"Ducts, conduits, pipes, or anything that penetrates the perimeter presents a vulnerability that must be addressed."
UFGS 13 49 20.00 10 §2.4.4, §2.4.6
DoD guide specification, RFI/EMI Shielding
"Do not use self-tapping screws for attachment of shielding." "Seal penetrations of the shield, including bolts or fasteners, with puddle welds or full circumferential EM welds."
MIL-HDBK-1195 §5.3.2
Historical
"Penetrations of the shielding by screws, nails, bolts and other items shall be prohibited."
In Compliance Magazine
Practitioner
Screwing the second drywall layer "penetrates the RF shielding, thus creating the potential for RF shielding leakage." Ceiling rods and angles "may result in hundreds, if not thousands, of penetrations."
Why one screw matters. The fastener leaves a hole plus a metal stub that carries current through the skin and re-radiates it on the other side. Foil can tear or corrode around it over time. Holland Shielding adds that a wire not fully connected to the shield "will work as an antenna."
You won't see the leak. MIL-HDBK-1195 §5.1.1: "leaks in a shielded enclosure cannot be detected by visual inspection." Only instrument testing finds them.
The weld-over in UFGS is the shield vendor's detail, not a field fix. Only the shield designer decides whether a fastener is sealed by welding, and only on shields designed for it.
The door contact still has to meet every IDS rule. The mount only changes how it's attached.
The mount must still deliver
Text
Source
Listed switch
"UL 634 HSS level 2. Level 2 rated switches only include Balanced Magnetic Switches that pass additional performance testing."
UFC 4-010-05 §3-4.17.3.3
Coverage
"SCIF perimeter doors shall be protected by an HSS and a motion detection sensor."
Tech Spec 7.A.3.a(7)
Cabling
"…dedicated to the system, contained within the perimeter, and comply with Committee for National Security Systems (CNSS) standards."
UFC 4-010-05 §3-4.17.3.4
Performance
The alarm must activate before the non-hinged side of the door opens beyond the door's thickness
Tech Spec 7.D.3
Default for an RF-shielded door (design reasoning, not a published requirement):
Surface HSS on the protected side, on the switch maker's bracket, fastened to the door maker's hardware prep or to an interior strut. Never fasten through a frame that forms part of the shield.
Magnet on the inside face of the leaf, clear of the knife-edge, finger stock and seals.
Armored leads into surface raceway, then to the IDS panel inside.
Only filtered or fiber-converted circuits cross the penetration panel.
Install before the final shield test, so the test covers the room as it will be used.
On an STC-rated (acoustic-only) door, the same side logic applies. Screws must not reach acoustic fill or compress or bridge the seals.
Placement. Mount near the latch-side head corner so the 7.D.3 thickness test passes on heavy, thick doors. Keep brackets clear of door bottoms, gaskets, finger stock and knife-edges. A bracket that holds the door slightly open fails both the STC and RF tests.
Gap drift. Sag, cam-lift motion and seals taking a set all change the switch gap. Re-check at turnover and at each semiannual IDS test.
Pick the method from the door and shield details, then confirm it with the shield vendor, the door maker and the switch maker. Rows marked derived are installer reasoning from the sources, not published approvals.
Method
When to use
Risk
Notes
Surface HSS on the protected-side face of the frame head, magnet on the door's top rail
Standard SCIF doors; factory-prepared frames
Screws pass through a shield-forming frame or into acoustic fill or seals (derived)
Use the door maker's hardware prep; confirm what's behind the face before any fastener
Manufacturer Z- or L-bracket
Out-swing doors, deep acoustic frames, drop-seal housings, knife-edge frames
A flexing bracket changes the gap. Third-party brackets may raise listing questions (unverified)
Use a rigid bracket fastened to factory prep or an inside steel plate
Non-ferrous spacers or shims
Steel doors and frames, seal thickness, uneven faces
Gap changes once seals take a set
Re-check the gap after seals set, then retest to 7.D.3
Strut or standoff frame inside the shield
Welded or modular shields where nothing may touch the skin
Strut touching the shield creates an unplanned ground path
Anchor to structure inside the shield or to vendor-approved points only. Welded attachment studs aren't confirmed as a universal option
Furred chase or secondary stud wall
Many devices in one area; recessed boxes wanted
Hides the boundary; some AOs dislike it (practitioner)
Allowed by Tech Spec 3.G.5 and UFC 3-4.4.7. Must be self-supporting
Surface raceway or surface EMT
Retrofits; wherever inspectability matters
Fasteners driven through the shield
Fasten to furring, strut or approved points. On acoustic-only walls, surface fastening into the finish board is the normal Tech Spec approach (derived)
Adhesive or epoxy
Raceway clips and tie mounts, only where the shield vendor approves
No fetched UL 634 Level II document describes adhesive mounting of the switch
Not a method for the switch itself; see the adhesive section below
The installation sheet for the exact switch model governs. Magnasphere's UL 634 Level 2 documents were publicly fetchable, so they're the worked example here. Other makers' install sheets weren't reviewed.
Concealed model (HSS L2C):
"installation must be in a metal frame" for UL compliance.
"Prepare a deburred 1" hole directly opposite to the mounting site of the magnet module."
"All wires must route within the metal frame."
Maximum operating gap stated as 1/8 in (3.2 mm).
"The tamper circuit (if equipped) must be wired to a 24-hr protection circuit."
Consequence: a concealed contact means drilling the frame and running wire inside it. Never field-drill a shielded or knife-edge frame for a concealed switch. Use a surface model on the protected side, or a frame the RF door maker prepared at the factory.
Surface models (L2S/L2D CSI specification):
"Universal cross-hole mounting for in-swing or out-swing door installations," with #10 screw holes.
An integrated removal tamper that alarms when the switch is removed from its mounting surface.
Leads with "stainless steel armored jacket or conduit."
Execution: "Per Manufacturer's Instructions."
Removal tamper depends on a mechanical mount. The tamper document says the tamper magnet "is inserted into this mounting hole" and capped. The switch is designed to be screwed down over it.
Magnet warning. The magnets are "extremely powerful: Take precautions to avoid the magnetic attraction between the magnet and ferrous metals." Steel doors and frames alter the field, which is why spacers exist.
Listed accessories (Magnasphere part numbers): HSS L-Bracket (1625), HSS Z-Bracket (1620), Adjustable Magnet Bracket (1229), plastic shims (SP062) and aluminum shims (SP062-FIRE), 1" magnet housing spacer (1102), 3" magnet module spacer (1731), 1/4" aluminum spacer (1578), Armored Cable Routing Clamps (1807), Tamper Test Magnet (1384), plus roll-up and overhead door bracket kits.
Nuisance alarms. NAVFAC design manual DM-13.02 notes that door movement from wind or pressure causes nuisance alarms on balanced magnetic switches. Pressurized vestibules and heavy acoustic doors are candidates.
Double-sided tape and construction adhesive look like an easy way to avoid a hole. For a UL 634 Level II high-security switch on a SCIF door, they aren't a documented option.
What the research found:
No fetched UL 634 Level II document describes adhesive mounting of the switch or its magnet.
The surface-mount specification calls for screw mounting through cross holes, and execution "Per Manufacturer's Instructions."
The removal tamper relies on a magnet "inserted into this mounting hole." A switch stuck to a surface has nothing for that tamper to detect in the way the design intends. An adhesive-only mount defeats that design.
Adhesive bonds creep, soften with heat and let go as seals and doors move. A gap that drifts can fail the 7.D.3 test months after acceptance.
Where adhesive does appear. ETS-Lindgren's architectural shielding foil is itself set with "Vinyl-to-vinyl adhesive (or equivalent)." That's a shield material detail from the shield maker. It doesn't make adhesive an approved way to attach security devices, and adhesive compatibility with a particular foil or finish wasn't confirmed.
What to do instead:
Screw the switch to a manufacturer bracket, spacer or strut that's fastened where the shield vendor and door maker allow.
If a raceway clip or cable tie mount really must be adhered to a treated surface, get the shield vendor's written approval of the product and the surface first.
Keep the switch's removal tamper functional and wired to a 24-hour zone.
Once a device is mounted, its cable has to reach the single point of entry without touching or piercing the shield along the way.
Rules for the route:
Rule
Text or basis
Source
Every crossing line is treated
"Provide a filter for each power, data, and signal line penetrating the enclosure."
UFGS 13 49 20.00 10 §2.7
IDS cabling stays inside
"…dedicated to the system, contained within the perimeter…"
UFC 4-010-05 §3-4.17.3.4
Cabling that leaves the SCIF
"…shall employ Encrypted Line Security or be installed in a closed and sealed metal conveyance… ferrous Electrical Metallic Tubing (EMT), ferrous pipe conduit or ferrous rigid sheet metal ducting."
Tech Spec 7.A.2.e (v1.4 text; verify against v1.5.1)
One entry, labeled
"Cabling must enter the protected area from a single location and must be identified and labeled with its purpose and destination at the point of entry."
UFC 4-010-05 §3-4.19
Seal both sides
"Seal both sides of perimeter penetrations," finished to match the adjacent surface
UFC 4-010-05 §3-4.11.3
Spares
Expansion conduit "filled with acoustic fill and capped"
Tech Spec 3.G.6
How it works in the field (installer practice derived from the rules):
Device to raceway. Armored switch leads go into surface raceway or surface EMT on the protected side. Use the switch maker's armored cable clamps where supplied.
Raceway supports. Fasten to furring, strut or vendor-approved points, never through foil, sheet steel or shield panels. On acoustic-only walls, surface fastening into the finish board is the normal approach.
Keep off the skin. Interior conduit and strut don't touch the shield except at designed bonds.
At the panel. Low-voltage circuits cross only through signal filters, or convert to fiber and pass through a waveguide. Copper, PoE, armored fiber and steel fish tape never go through a waveguide.
Spares. On an RF shield, a spare also needs an RF closure the shield vendor details and the test covers. The acoustic cap alone isn't enough.
Non-shielded perimeter. The same single-entry, labeling and two-side sealing rules apply. Metallic conduit gets whatever break or grounding the TEMPEST Countermeasure Review directs.
Installers hear opposite advice about metal conduit where it meets a shield. Both views are published.
View
What it says
Source type
Bond it continuously
"The penetration through the shielding must be metal, and continuously bonded electrically around the periphery of the penetration to the shielding (welded or brazed)." "Clamped or threaded penetrations, and those using RF gaskets are not projected to provide long term electrical continuity because of oxidation and corrosion of closure contact surfaces under normal environments."
MIL-HDBK-1195 §2.6.4 (Historical)
Don't bond building metal to the shield
Bonding the shield to conduit, plumbing and ducts "does not represent a best practice for RF shielding and will likely reduce the overall shielding performance." Recommends fiber through inexpensive waveguides for data.
In Compliance Magazine (practitioner)
Why they aren't really contradictory. The handbook describes how a penetration that must be metal is made part of the shield: welded or brazed all the way around, by the shield builder. The practitioner warns against tying the shield to building conduit and piping in general, which creates unplanned current paths. Both reject casual clamp-on bonds.
The resolution:
Build each penetration exactly as the shield designer details it. Weld, braze, filter, waveguide or dielectric section: whatever the drawing shows, and nothing else.
Keep interior conduit and strut off the shield everywhere except the designed bonds.
Never improvise clamp or gasket bonds at the shield, even when an inspector or a code habit suggests a jumper.
Prefer fiber for data where the design allows, so fewer metallic lines cross at all.
Ask before bonding anything to a shield. An unrequested jumper can create a second ground path.
At a non-shielded perimeter the logic is different. UFC 4-010-05 §3-4.11.2, "Unless directed otherwise by the TEMPEST Countermeasure Review," gives metal conduit or pipe "a nonconductive union inside the perimeter adjacent to the penetration," or grounding near the penetration with a No. 4 wire to the building grounding system.
When a room needs many outlets, readers, speakers or panels on a treated perimeter wall, the cleanest answer is often a second wall in front of it.
What the rules allow:
Tech Spec 3.G.5 permits "an additional wall… constructed using furring strips as stand-off from the existing wall assembly."
UFC 4-010-05 §3-4.4.7 says to "construct a furred out wall for routing of utilities," which is what makes recessed outlet boxes and recessed panels acceptable.
Build rules (installer practice derived from the rules and shield details):
Rule
Why
The furred wall is self-supporting from floor and structure, not screwed through the treated layer
Otherwise the furring just moves the penetrations
Metal studs or tracks that bear on a shield are isolated per the shield detail
Incidental contact creates unplanned ground paths
Boxes, back boxes and anchors stay inside the furred cavity
The treated wall behind stays intact
Cables still route to the single point of entry
A furred wall is a chase, not a new entry
Photograph the treated wall and the chase before board goes on
UFC 4-010-05 §4-7 calls for a photographic record of perimeter penetrations and wall assemblies
The inspectability tradeoff. Some AOs dislike furred walls because they hide the boundary (practitioner, Milham). UFC §3-4.1.1 asks designers to minimize "above ceiling obstructions on the controlled and uncontrolled side of the secure perimeter." Surface raceway versus furring is an AO preference, so settle it at design review.
Hardening layers. On walls with expanded metal or plywood for forced-entry resistance and visual evidence of penetration, don't cut or notch the layer for cable. Plan the entry point before the layer goes in, using an AO-approved detail. An unexplained patch is exactly what inspectors look for.
Interior (non-perimeter) sound-rated walls. Recessed boxes aren't allowed on treated perimeter walls. Practitioners report that interior compartment walls may carry them if the design keeps the rating; confirm with the AO, and note UFC 4-010-05 §3-4.4.8 still prohibits recessed fire extinguisher cabinets on sound-rated compartmented area walls. Offset boxes on opposite faces and use listed putty pads. Non-rated smoke and acoustic cable pathways exist, for example STI EZ-Path 44NEZ, described as "high-performance acoustical separation." Follow the rated-assembly listing and the acoustician.
The primary entrance needs a reader outside the door, which puts a device and its cable on the uncontrolled side. The Tech Spec controls what can be reachable there.
Topic
Text
Source
Minimum
"At a minimum, provide card reader with keypad at the primary entrance and when provided, the secondary entrance."
UFC 4-010-05 §3-4.17.1
Tamper and fastening
"Card readers, keypads, communication interface devices, and other access control equipment located outside the SCIF shall be tamper-protected and be securely fastened to a wall or other fixed structure."
Tech Spec 8.C.1 (v1.4 text)
Wiring access
"Electrical components, associated wiring, or mechanical links shall be accessible only from inside the SCIF."
Tech Spec 8.C.2 (v1.4 text)
Reader data
Data "to and from equipment located outside the SCIF shall be protected using FIPS AES certified encrypted lines. If this communication technology is not feasible, transmission lines shall be installed as approved by the AO."
Tech Spec 8.C.3 (v1.4 text)
Software
"…located in the SCIF or a SECRET controlled area."
Tech Spec 8.C.4 (v1.4 text); UFC §3-4.17.1
Applying it (installer practice derived from the rules):
Mount the reader over a small dedicated penetration so the cable goes straight into the SCIF.
Nothing reachable outside: no exterior junction box, splice, exposed conduit or terminal strip.
Use tamper-resistant fasteners and wire the reader's tamper output.
Seal the penetration on both sides.
Treat the reader data path as a line to outside equipment: encrypted or AO-approved. Don't describe a protocol as "FIPS AES certified" without the product's certificate.
On an RF shield, the reader cable is a conductor crossing the shield. It goes through a signal filter or a fiber conversion at the penetration panel, as the shield designer details. Don't pass it through the door frame.
An electrified lock or trim on the leaf needs power and signal carried from the frame. On an RF or heavy acoustic door, the path matters.
What the published sources say:
UFGS 13 49 20.00 10 §2.6.1.5–.6: "Install electric connectivity for sensors, alarms, and electric interlocking devices in accordance with the door manufacturer's instructions, the approved drawings, and Section 26 20 00…" Vestibules with shielded doors at each end get electric interlocks.
UFC 4-010-05 §3-4.6.5: electric strikes or electrified mortise locks with an ACS "must have a positive engagement, fail secure, and approved under UL 1034."
UFC 4-010-05 §3-4.6.6: hinges "reinforced to a minimum of 7 gauge, and be cam-lift for acoustical door assemblies."
ETS-Lindgren's DKE RF door uses "Three heavy-duty aluminum hinges… six thrust bearings" and lists options including "Interface with Security Systems," "Emergency Release" and "Battery Back-up Upgrade."
Comparison (design reasoning, not a published requirement):
Factor
Power transfer hinge
Armored door loop
Conductor path
Concealed in the knuckle
Exposed loop on the protected side
RF or STC note
Never pass wire through the knife-edge or finger-stock interface
Same; keep the loop wholly on the protected side
Cam-lift acoustic doors
Electrified cam-lift models in heavy weight classes may not exist (unverified)
Works with any hinge
Heavy RF leaves
The hinge carries load; swapping one may void door performance (unverified)
Carries no load
Inspection
Hidden
Visible, and must not be reachable from outside
Best practice
Factory-prepared by the door maker
Protected-side surface mount
Why the door maker controls this. Historical MIL-HDBK-1195 §2.6.2.1 notes that some manufacturers "refuse to guarantee performance of their door and door frames in shielding provided by others, unless they are in control of the door installation."
Steps:
Get the door maker's wiring path and interface diagram as a submittal before assigning IDS or ACS points.
Route lock and sensor conductors to the penetration panel, not through the frame into the uncontrolled side.
The RF door is the most delicate part of the shield, and it's installed while the dirtiest trades are still working.
Protection during construction (installer practice):
Cover the knife-edge and finger stock with the door maker's guards or rigid covers. Don't tape directly to finger stock.
No welding, grinding or spray painting near an uncovered RF frame. Mask the contacts before painting the frame.
Don't prop the leaf with wedges that crush fingers. Use the door's own hold-open provisions or keep the leaf closed.
Keep carts and material off the threshold.
Log any damage and let the door maker repair it.
Sequencing for low-voltage work:
Door hung, balanced and adjusted by the door maker.
HSS brackets, magnets, electrified hardware and raceway attachments installed, or at least mocked up at their final fastening points.
Confirm nothing holds the door off its seals.
Shield test.
Walk-test the HSS to Tech Spec 7.D.3 after seals have set.
Why it matters. A practitioner in the door and lock trade writes: "Most SCIF doors fail to pass accreditation as a result of poor installations, not defective products." A test run before hardware goes in describes a door that no longer exists.
Mistakes happen: a drill walks, a hanger goes in the wrong place, a tech mounts a box before reading the drawing. What turns a mistake into a failed accreditation is hiding it.
The response:
Step
Action
Basis
1. Stop
Stop work at that location. Don't remove the fastener unless the shield vendor says to.
Installer practice
2. Report
Tell the GC, the SSM and the shield vendor the same day. Photograph it with a location reference.
UFC 4-010-05 §4-7 photographic record
3. Don't cover
Never caulk, tape or paint over a shield hole. Sealant doesn't restore conductivity and hides the leak.
Installer practice
4. Vendor repair
The shield vendor repairs with its own method: welding on steel shields, its approved patch on foil systems. The specific foil repair method wasn't confirmed in public sources.
Shield vendor detail
5. Retest
Retest the affected area, or the room, as the vendor and CTTA direct.
See Historical note below
6. Record
Log the event, repair and retest in the shield-change log and the construction record.
UFC 4-010-05 §4-7
7. Notify
If the room is already accredited, the SSO and AO decide what notification and review applies.
Why reporting protects the installer. During construction, the SSM must "Document security violations or deviations from the CSP and notify the AO within 3 business days." A practitioner guide on accreditation adds that "Any deviations from the approved design, no matter how minor, must be documented and approved." A reported, repaired and retested hole is a record. A hidden one is a finding.
Hold points stop the job until someone verifies conditions that will soon be hidden or tested. The Tech Spec requires periodic SSM inspections, but it doesn't list these specific points. They're recommended practice built from the sources cited.
Hold point
When
What to verify
Evidence
1. Coordination
Before rough-in
Shield vendor and door maker attachment, wiring and interface details received; penetration schedule frozen
Approved submittals
2. Hardening layer
Before expanded metal or plywood goes in
Cable entry points planned with an AO-approved detail
Marked-up drawing
3. Pre-cover
Before board closes
In-wall and above-ceiling conditions: supports, boxes, conduit, sealant, penetrations; no fasteners through treated layers
Photo record per UFC 4-010-05 §4-7
4. Shield walk-down
After interior raceway and furring, before finishes
Strut and conduit isolated; bonds only where detailed; no copper in waveguides; spares closed
Walk-down checklist signed by GC and shield vendor
5. Pre-test
Before the shielding effectiveness test
Doors hung and balanced; filters and waveguides in; HSS brackets, electrified hardware and raceway attachments installed or mocked up
Shield vendor readiness sign-off
6. Post-test
After a passing test
Any later change goes through review and retest; HSS walk test after seals set; tampers on 24-hour zones
Shield-change log; IDS acceptance records
Who attends. A practitioner build sequence recommends the SSM, and the AO or TSCM if they ask, inspect in-wall and above-ceiling conditions before board closes. UFC 4-010-05 §4-7 calls for "a photographic surveillance record documenting construction progress at critical areas such as perimeter penetrations, door installations, and wall assemblies."
What it set out to do (§1.1): "This handbook provides guidance with the RED/BLACK concept for the engineering and installation of systems and facilities processing classified information." It covered power distribution, equipment installation, signal distribution, filters and isolators, grounding, bonding and shielding, physical security and administrative telephones.
Two ideas (§4.1). RED/BLACK means components "processing classified plain text information be kept separate from those that process encrypted or unclassified information." TEMPEST means controlling compromising emanations. The handbook teaches six techniques: grounding, bonding, shielding, physical separation, physical protection and filtering or isolation.
The honest limit (§4.1). The handbook assumes low-level balanced signaling. It acknowledges that facilities designed to RED/BLACK criteria may still have TEMPEST deficiencies, and that post-installation TEMPEST testing may require additional measures.
Lessons for installers:
Following a guide doesn't guarantee a TEMPEST pass. Equipment, signaling and workmanship all matter.
"Constant attention is required to ensure proper separation, isolation, and accountability" (§4.1 design verification).
Bonds matter: a good bond means "the impedance through the connection is not appreciably greater than the impedance in the conductors themselves" (§4.6.2). Welding is preferred, and split bolts are "not recommended."
Filters belong where the design puts them: "In no case should a line be multifiltered between two points" (§5.4.5).
Build to the CTTA's review and the drawings, and expect that testing may add work.
Purpose. "This instruction establishes guidelines and procedures for determining the applicable countermeasures for national security systems. This instruction applies to all federal departments and agencies and their agents, which include, but are not limited to, contractors, consultants, and licensees."
Key concepts:
Concept
Text
Inspectable space
"The three-dimensional space surrounding equipment that process classified and/or sensitive information within which TEMPEST exploitation is not considered practical or where legal authority to identify and/or remove a potential TEMPEST exploitation exists."
Authority
"A CTTA must conduct or validate all TEMPEST countermeasure reviews required by this instruction."
Selection logic
"…the CTTA will recommend the most cost effective countermeasure which will contain compromising emanations within the inspectable space to the decision authority designated by the department/agency head."
Records
"The CTTA shall maintain a record of all TEMPEST countermeasure reviews conducted, recommendations provided and estimated cost of implementation."
Review factors (Annex B)
Location; volume by classification; sensitivity; perishability; physical and access controls; equipment TEMPEST profiles
The teaching logic:
Define the inspectable space.
Weigh the factors.
The CTTA recommends the least-cost countermeasure that's adequate.
The agency's designated authority decides.
What it means on a jobsite today. Integrators and GCs build to the CTTA's current TEMPEST Countermeasures Review and the approved drawings. Don't add shielding, filters or breaks "to be safe." The Tech Spec says "Exceeding a standard, even when based upon risk, requires that a waiver be processed and approved," and a waiver can take the facility out of mandatory reciprocity. Don't advertise a room as "TEMPEST compliant."