ICD 705ICS 705-1 / 705-2TECH SPEC v1.5.1UL 2050 · EXTENT 3
SCIF & SAPF
Security Primer
Public Edition. How accreditation, construction, intrusion detection, access control, acoustics and RED/BLACK discipline fit together, in plain English, with the published requirements behind every point.
Read this first · Important notice
Educational, public-level information. This primer explains the published, publicly released baseline for Sensitive Compartmented Information Facilities (SCIFs) and Special Access Program Facilities (SAPFs). It is not a design standard, a specification, legal advice or a substitute for the documents it cites.
- Not affiliated with or endorsed by ODNI, NCSC, DoD, DCSA, DIA, NSA or UL Solutions. Names of agencies, standards and products are used for identification only.
- Your AO / CSA / CTTA sets requirements. Your Accrediting Official, Cognizant Security Authority and Certified TEMPEST Technical Authority decide what applies to your facility, and their written direction controls your project.
- Nothing here is FOUO, CUI or classified. Restricted TEMPEST documents are named but never reproduced. No RED/BLACK separation distances, shielding attenuation requirements, facility addresses or filled-in checklists appear in this document.
- Historical documents are labeled. Superseded or FOIA-released material is cited for context only, never as a current requirement.
Do not send classified information, CUI or facility addresses by unencrypted email, including to us. The combination of an address and “SCIF” is itself protected information in DoD. Ask your AO for the approved channel.
How to use this primer
Chapters 1–5 are the frame: what a SCIF is, the documents, the people and the accreditation path. Chapters 6–14 follow the build from perimeter to turnover. Chapter 15 collects the traps that most often delay accreditation, and Chapters 16–17 are the glossary and the official reference library with links.
Paragraph citations (for example Tech Spec 3.G.7 or UFC 3-4.6.5) let you find the exact text in the source. Every chapter ends with its sources. Current versions used throughout: ICD 705 (26 May 2010), ICS 705-1 (17 Sep 2010), ICS 705-2 (22 Dec 2016), IC Tech Spec v1.5.1 (26 Jul 2021), DoDM 5205.07 consolidated (17 Jan 2025), UL 2050 Edition 6 (7 Apr 2025), 32 CFR Part 117 and UFC 4-010-05 (26 May 2023).
SCIF & SAPF Security Primer · Public Edition
September 2026 · Content current to public sources checked September 2026
Published by LA CCTV Supply · PO Box 4327, La Puente, CA 91747 · 1-626-789-2267 · lacctvsupply.com
Reading the callouts
Who this is for
| If you are a… | Start with |
|---|---|
| Owner or sponsor | Ch. 1, 4, 5 and 15 |
| Architect / engineer | Ch. 6, 8, 9 and 12 |
| General contractor | Ch. 7, 8, 14 and 15 |
| Low-voltage installer | Ch. 10, 11, 12 and 13 |
| Security manager | Ch. 3, 4, 10 and 13 |
Figures
All figures are original schematic illustrations drawn for teaching. They are illustrative and not to scale. Build only to your stamped, AO-approved drawings, the CTTA’s TEMPEST Countermeasures Review and manufacturer installation instructions.
Companion download
RED/BLACK, Filters & Shield Penetrations: Field Guide for GCs & Installers expands Chapter 12 with installer methods: line vs load, bonding, stored charge, waveguides, fiber entries, fastening without breaching the shield, and pre-test hold points.
The one-sentence version
A SCIF is proven, not purchased: an Accrediting Official accredits a documented facility after the right people approved the design, watched the build and tested the systems.
Three gates that never move
Coordinate with the AO before design, orders or contracts. No construction award without an approved CSP. No SCI in the space before the accreditation letter.
Three things nobody can certify
A product as “ICD 705 certified.” A room as “TEMPEST compliant” without a CTTA. A panel as “UL 2050 listed”: UL 2050 certifies the alarm service company.
Chapter 01Foundations
What SCIFs & SAPFs are
A SCIF is a room, suite or building that a government Accrediting Official has formally approved for Sensitive Compartmented Information. The approval, not the construction, makes it a SCIF. A room built “to ICD 705” but never accredited is just an expensive room.
Accreditation, not construction
ICD 705 (26 May 2010) requires that SCI be handled only in accredited SCIFs, that SCIFs meet uniform Intelligence Community (IC) standards, and that they be built for reciprocal use across IC elements. Facilities must be accredited before SCI operations begin. DoD puts it bluntly: “SCI will not be discussed or introduced into the proposed SCIF until the facility is accredited” (DoDM 5105.21 Vol. 2).
Every SCIF also has a mode (closed storage, open storage or continuous operation) and may be a lesser type (SWA, TSWA, T-SCIF). Those choices drive walls, alarm response and cost (Chapter 5).
Where SAPFs fit
A Special Access Program Facility (SAPF) protects SAP information. Its current governing manual is the consolidated DoDM 5205.07 (17 Jan 2025), which cancelled the 2015 Volume 3 on physical security. A SAPF Accrediting Official, appointed in writing by the Cognizant Authority SAP Central Office, approves preconstruction plans and inspects and accredits the facility.
SAPFs are built to the equivalent Tech Spec criteria, and DCSA’s January 2026 SAP checklist cites Tech Spec Chapter 7 throughout for SAPF intrusion detection. A SAPF may be accredited as a SCIF after the AO reviews all required SCIF construction documentation (Tech Spec 1.B.2). Moving SAP into a SCIF, or SCI into a SAPF, requires a Co-Use Agreement first.
What a SCIF is not
- A NISPOM open storage area (formerly “closed area”): protects collateral classified information and is approved by DCSA. SCI cannot enter without SCI accreditation.
- A GSA-approved container: storage equipment, not a facility. A closed storage SCIF uses containers inside an accredited perimeter.
- A vault: a construction method (Tech Spec 3.C.5; FED-STD 832) that may sit inside or form part of a SCIF.
- A “SCIF-ready” modular product: the Tech Spec warns such claims “may not be accurate.”
- An RF-shielded room: shielding is one possible TEMPEST countermeasure a CTTA may recommend. It accredits nothing.
Table 1.3 · Acronyms that mean two things
| Term | In ICD 705 / IC documents | The other meaning you will meet |
|---|---|---|
| SSM | Site Security Manager: owns security during planning, design and construction; writes the CSP | Used loosely for whoever runs day-to-day SCIF security (that is the SSO / SSR or CSSO) |
| CSA | Cognizant Security Authority: the official over the SCI security program | NISPOM Cognizant Security Agency: DoD, DOE, NRC, ODNI, DHS |
| CSSO | SCI: Contractor Special Security Officer | SAP: Contractor SAP Security Officer |
| CUA | Co-Use Agreement between AOs (Tech Spec 12.N–P) | Misread as a “controlled unclassified area” |
| AO | Accrediting Official for the facility | Authority to Operate (ATO) for a networked system under RMF, a separate approval |
| Extent | UL 2050 Extent 3: an alarm installation designation | Not a TEMPEST, RF or acoustic rating; web “Extent 1–5” ladders conflict with 32 CFR 117.15 |
Table 1.1 · SCIF vs SAPF vs NISPOM open storage area vs GSA container · published baselines; many items are left to AO or CSA determination, and exceeding a published standard requires a waiver
| Attribute | SCIF | SAPF | NISPOM open storage area | GSA-approved container |
|---|---|---|---|---|
| Protects | SCI | SAP information | Collateral classified (contractor) | Collateral; SCI when inside a closed storage SCIF |
| Governing documents | ICD 705, ICS 705-1/-2, IC Tech Spec; DoDM 5105.21 in DoD | DoDM 5205.07 (17 Jan 2025), built to equivalent Tech Spec criteria | 32 CFR 117.15; construction per 32 CFR 2001.53 | 32 CFR 2001.43; DoD Lock Program specs |
| Who approves | IC element AO (DIA for most DoD and DoD contractors) | SAPF Accrediting Official | DCSA approves the space and IDS before installation | Must be GSA-approved; supplemental controls per 2001.43 |
| IDS installation | UL 2050 Extent 3 TS 7.A.2.b | UL 2050 Extent 3 DCSA F-30 | Extent 3 baseline; Extent 5 only with CSA approval | No IDS sensors on the container itself 117.15(d)(4) |
| Alarm response (TS / SCI) | Closed 15 min; open 15 min with SID, 5 min without | Same as SCIF | TS open storage: 15 min with SID, 5 min without | 2-hour checks, or IDS with 15-min response, or SID + FF-L-2740 lock |
| Reciprocity | Mandatory across IC elements if no waivers | May be accredited as a SCIF on documentation review; co-use needs a CUA | Not applicable | Not applicable |
Table 1.2 · The three things every accreditation package proves
| Pillar | What must be demonstrated | Typical evidence | FFC v1.5 sections |
|---|---|---|---|
| Physical | The perimeter resists and shows evidence of penetration; doors, locks and penetrations meet the Tech Spec; speech does not leave the room | As-built drawings, wall and penetration details, photographic construction record, door and hardware schedule, acoustic test data | B Security-in-Depth · C SCIF Security · D SCIF Doors · G Acoustical Protection |
| Technical | Intrusion detection, access control, telecom and emanations risks are controlled | UL 2050 certificate, IDS spec sheets and acceptance tests, encryption certificate, telecom baseline, TEMPEST Checklist and the CTTA’s review | E IDS · F Telecom Systems & Equipment Baseline · I INFOSEC / TEMPEST / Technical Security |
| Procedural | People run the space correctly every day | SOP, emergency plan, Construction Security Plan, destruction methods, visitor and combination control, end-of-day checks (SF 701/702) | A General Information · H Classified Destruction Methods · plus SOP and plans |
SourcesICD 705·IC Tech Spec v1.5.1·DoDM 5105.21 Vol. 2·DoDM 5205.07 (2025)·32 CFR 117.15·32 CFR 2001.43·DCSA SAP Checklist (Jan 2026)·UFC 4-010-05
↑ Back to contentsChapter 02Foundations
The document stack
One directive sets policy, two standards set the rules, and one technical specification tells you how to build and run the space. DoD, the State Department and the SAP community layer their own manuals on top. Read top-down for authority and bottom-up for method.
The Tech Spec, chapter by chapter
Chapter 1 Introduction · 2 Risk management (SID, compartmented areas) · 3 Fixed facility construction (inside the U.S.) · 4 Outside the U.S., not under Chief of Mission · 5 Under Chief of Mission · 6 Temporary, airborne, shipboard · 7 Intrusion detection · 8 Access control · 9 Acoustics · 10 PEDs · 11 Telecommunications · 12 Management & operations · 13 Second Party integree & liaison spaces (new in v1.5.1) · 14 Forms and plans.
The v1.5 and v1.5.1 change histories list no Chapter 7 (IDS) changes. Co-use sections N–P sit above the Chapter 13 heading in the v1.5.1 contents but belong to Chapter 12 (12.N–12.P).
Version traps that show up in specs and proposals
- “The 2020 Tech Spec.” That is v1.5 (cover date 13 Mar 2020). The current public version is v1.5.1, which moved Forms and Plans to Chapter 14.
- “DoDM 5205.07 Volume 3 governs SAPFs.” Volume 3 (23 Apr 2015) was cancelled by the consolidated manual effective 17 Jan 2025.
- “Extent 3 is in the Tech Spec.” Extent 3 is a UL 2050 installation designation; Tech Spec 7.A.2.b points to it.
- “DCSA will accredit our SCIF.” DCSA administers the NISP for collateral work. It does not accredit SCIFs or SAPFs.
- “NISPOM closed area.” 32 CFR Part 117 replaced closed areas with open storage areas. UL’s alarm form still says “closed area.”
- “Exceeding the standard is always safe.” Tech Spec 2.A: exceeding a standard, even based on risk, requires a waiver, and a waiver ends mandatory reciprocity.
Table 2.1 · Current public versions, checked September 2026
| Layer | Document | Current public version | What it does |
|---|---|---|---|
| Directive | ICD 705, SCI Facilities | 26 May 2010 | SCI only in accredited SCIFs; AO and waivers; reciprocity |
| Standard | ICS 705-1, Physical & Technical Security | 17 Sep 2010 | The “shall” standards: perimeter, IDS, ACS, TEMPEST, PEDs, telecom |
| Standard | ICS 705-2, Accreditation & Reciprocal Use | 22 Dec 2016 | Accreditation, re-evaluation, de-accreditation, co-use |
| Specification | IC Tech Spec for ICD/ICS 705 | v1.5.1, 26 Jul 2021 | Build-to document; FFC, TEMPEST Checklist, CSP and other forms |
| DoD SCI | DoDM 5105.21 Vol. 2 | 2012, Change 2 (2020) | DoD SCIF physical security; DIA accredits for most of DoD |
| DoD SAP | DoDM 5205.07, SAP Security Manual | 17 Jan 2025 | Consolidated manual; SAPF physical security in Section 15 |
| DoD design | UFC 4-010-05, SCIF/SAPF Design | 26 May 2023 | A-E and GC design detail; implements, never overrides, the Tech Spec |
| Collateral | 32 CFR Part 117 (NISPOM) and Part 2001 | Current eCFR | Contractor safeguarding, open storage areas, IDS response |
| Alarm | UL 2050, National Industrial Security Systems | Ed. 6, 7 Apr 2025 | Alarm company certification; the Extent 3 installation |
| State Dept. | 12 FAM 710; OSPB standards in 12 FAH-6 | Current FAM | Chief of Mission SCIFs; the more stringent standard applies |
SourcesNCSC Security Governance & Regulations·ICD 705·ICS 705-1·ICS 705-2·IC Tech Spec v1.5.1·DoDM 5205.07 (2025)·UFC 4-010-05·UL 2050 Ed. 6·12 FAM 710·SAME 2026 (practitioner)
↑ Back to contentsChapter 03Foundations
Roles & responsibilities
Three groups touch every SCIF. Deciders approve: the IC element head, AO, CSA, the CTTA for TEMPEST and the AHJ for life safety. Security staff plan and run the space: SSM, SSO, SSR, CSSO and CSTs. Builders produce the evidence: designer, general contractor and integrator. Builders never approve their own work.
Separation rules that invalidate approvals
- The AO does not grant waivers. ICD 705: “In no case may this official be the same person as the Accrediting Official.” Approved waivers are reported to the Director, NCSC within 30 days.
- The CTTA recommends; the AO approves. Integrators, shielding vendors and architects do not decide TEMPEST countermeasures.
- SSM means Site Security Manager in ICS 705-1 and the Tech Spec: planning, design and construction only. Operations belong to the SSO/SSR (government) or CSSO (contractor).
- DCSA does not accredit SCIFs. DIA provides physical and TEMPEST accreditation for DoD components and most DoD contractors; NSA, NGA and NRO accredit under their own cognizance.
- The GC cannot approve field changes to the perimeter. Deviations go through the SSM to the AO.
- The AO cannot waive a fire code. Life safety is the AHJ’s determination (Tech Spec 3.E.5), and neither office can waive the other’s requirements.
- A commercial bug sweep is not accreditation TSCM. TSCM for accreditation is requested through the AO and, as quoted in a practitioner summary (Armag) of Tech Spec 12.G.8, “will only be conducted by USG TSCM teams.”
Where a low-voltage integrator fits
The integrator’s work is some of the most heavily documented in the package, because the IDS is the detection layer when nobody is inside. What the public documents require of that scope:
- IDS installation, components and monitoring stations comply with UL 2050; installation is Extent 3 (Tech Spec 7.A.2.a–b).
- Contractor SCIFs “shall maintain a current UL certificate of installation and service,” renewed after IDS changes (ICS 705-1).
- Installation and testing inside the U.S. by U.S. companies using U.S. citizens (Tech Spec 7.D.1; UFC 1-18.1).
- System variables and passwords restricted to SCI-indoctrinated U.S. personnel (7.A.2.j); maintenance staff TOP SECRET-cleared or escorted, with repairs started within 4 hours of a trouble signal (7.C.2).
- The DoD package includes IDS specification sheets, the UL 2050 certificate, the NIST encryption certificate and IDS test results (DoDM 5105.21 Vol. 2).
An integrator does not accredit the space, approve the design, decide TEMPEST countermeasures or overrule life safety, and should never self-certify a room as “SCIF compliant.”
Table 3.1 · Who produces and who signs
| Role | Primary phase | Produces | Approves or signs |
|---|---|---|---|
| IC element head | All | Delegations | Original accreditation authority; waivers, or delegates them to a named senior official who is not the AO |
| Accrediting Official (AO) | All | Waiver requests; letters of accreditation | Design concept, CSP and final design; accreditation, re-accreditation, de-accreditation |
| Cognizant Security Authority (CSA) | Oversight | Repository data; re-evaluation schedule | Co-use concurrence; in DoD Services, concept approval and TSWAs/T-SCIFs |
| SAPF Accrediting Official | SAP facilities | — | SAPF preconstruction plans; SAPF accreditation (DoDM 5205.07) |
| Site Security Manager (SSM) | Planning → accreditation | CSP; inspection reports; violation notices to the AO within 3 business days; assembled accreditation documents | — (advises the AO) |
| SSO / SSR / CSSO | Operations | SOP, emergency plans, SF 701/702 records, posture-change reports, withdrawal requests | Occasional conference-room use without a Co-Use Agreement (SSO) |
| CTTA | Planning & design | TEMPEST Countermeasures Review (TCR) with recommendations | Recommends; the AO approves |
| CST, cleared guards, escorts | Construction | Surveillance logs; screening and escort records | — |
| TSCM team (U.S. Government) | As required | TSCM report | — |
| Designer of record (A-E) | Design | Drawings and project data for the SSM (UFC 1-19.1) | — |
| General contractor | Construction | Work per approved drawings and CSP; photographic record | — |
| IDS / low-voltage integrator | Install & test | UL 2050 certificate, spec sheets, acceptance test results, turnover records | — |
| Authority Having Jurisdiction (AHJ) | Design → occupancy | — | Building code, fire and accessibility compliance |
SourcesICD 705·ICS 705-1·ICS 705-2·IC Tech Spec v1.5.1·DoDM 5105.21 Vol. 1·DoDM 5105.21 Vol. 2·DoDM 5205.07 (2025)·UFC 4-010-05·Armag v1.5 summary (practitioner)
↑ Back to contentsChapter 04Foundations
The accreditation lifecycle
Accreditation is not a certificate you collect at the end of construction. ICS 705-2 calls it “the beginning of a life-cycle process of continuous monitoring and evaluation, periodic re-evaluations, and documentation reviews.” Most failures trace back to steps skipped at the start.
Plan: sponsor, concept, risk and TEMPEST
A SCIF exists to meet a government mission need, so every project needs a sponsor and an identified AO before design starts. For a DoD SCIF, the commander requests SCI from the Service CSA, designee or senior intelligence official, and “proof of sponsorship in the form of a SCIF number or written documentation of Concept Approval … is required” (UFC 4-010-05 2-2.1). SAPF sponsorship is generally formalized at the program level.
The AO and SSM assess “threats, vulnerabilities, and assets to determine the most efficient countermeasures” and document Security-in-Depth. The Pre-Construction Checklist (added in v1.5) gives the AO project data, points of contact and the “security in-depth starting point location.” If classified information will be processed electronically, the TEMPEST Checklist goes to the CTTA during planning, and the answer, the TEMPEST Countermeasures Review, may add filtering, dielectric breaks or shielding.
Design and approve: two gates before work
The AO must “review and approve the design concept, Construction Security Plan (CSP), and final design … prior to the start of SCIF construction” (Tech Spec 3.A). UFC 4-010-05 1-15 is blunt: “Do not award a construction contract without an approved CSP.” The CSP template’s baseline “may not be reduced without coordination and approval.”
Build and prove: the evidence trail
Inspectors cannot see inside finished walls, so the evidence is created now or never: SSM inspections for the duration of the project, violation notices to the AO within 3 business days, CST logs where required, and a photographic record of penetrations, door installations and wall assemblies (UFC 4-7). Systems testing produces the most paper: IDS acceptance tests (Tech Spec 7.D.3), the UL 2050 certificate, encryption certificates and acoustic results. The final FFC, SOP, emergency plan and (in DoD) catastrophic failure plan complete the package.
What the letter says, and what it does not
The letter of accreditation (ICS 705-2 §D.1.a) states the SCIF identity, type (for example open or closed storage), effective date, compliance with physical, TEMPEST and technical standards, and any waivers with the standard not met and when it will be. It enables SCI operations within that type and perimeter, reciprocal acceptance if there are no waivers, and co-use under a signed agreement. It does not authorize SAP, a different storage mode or a larger perimeter.
Operate: monitoring, re-evaluation, change
Continuous monitoring means SF 701 and SF 702 checks, random after-hours inspections at least monthly, posture changes reported to DIA’s accreditation office within 24 hours (DoD), and semiannual IDS tests with records kept two years. The CSA ensures periodic re-evaluations “or at least every five years” (ICS 705-2 §D.3.a). Re-accreditation is required for “major modifications to the SCIF, changes to the sensitivity of programs, or to the threat” (§D.4.b); in DoD that includes perimeter changes, storage-mode changes and leaving continuous operation.
Waivers, co-use and closeout
A waiver is limited to “exceptional circumstances” or a documented mission need to exceed a standard. The package states the standard affected, mitigations considered, justification, residual risk, compensating procedures, a compliance timeline and acceptance of lost mandatory reciprocity (ICS 705-1). DoD waivers normally last up to one year.
A Co-Use Agreement is signed by both parties’ AOs and is required for each contractor contracting effort; the tenant accepts the host accreditation and pays for changes it needs. Short-term exceptions: temporary SCI storage for another organization up to seven calendar days, and occasional conference-room use approved by the SSO. A SCIF de-accredited but held at SECRET for less than one year may be re-accredited (Tech Spec 1.B.1).
SourcesICS 705-2·ICS 705-1·IC Tech Spec v1.5.1·Pre-Construction Checklist v1.5·Fixed Facility Checklist v1.5·CSP v1.5·UFC 4-010-05·DoDM 5105.21 Vol. 2·CDSE SA501
↑ Back to contentsChapter 05Foundations
Facility types, modes & Security-in-Depth
“SCIF” is the family name. The storage mode decides where SCI sits when nobody is working; the facility type decides how long the space is accredited and whether it stores anything at all; Security-in-Depth decides how much credit the surroundings earn. Each choice changes walls, alarm response and cost.
Choosing a mode
Closed storage allows the standard wall and a 15-minute response without relying on SID. The trade-off is operational: every classified item, including equipment and media, goes into a container at the end of the day. UFC 4-010-05 is explicit that closed storage “includes all classified materials, equipment and information.”
Open storage lets equipment, media and documents stay in place, which suits operations centers and heavy IT use. The cost is either a qualifying SID layer the AO accepts, or hardened walls plus a response force that can arrive in five minutes, which in practice often means an on-site guard force. In DoD, changing storage mode later requires re-accreditation.
SWAs suit briefing rooms and conference space next to an existing SCIF: when unoccupied, all SCI is removed to containers “within a SCIF, a vault, or be destroyed.” A TSWA is part-time and short-term; its extension “requires a plan to accredit as a SCIF or SWA.”
Table 5.1 · Facility types at a glance
| Type | Definition (short) | Storage? | Duration | SAP twin | Source |
|---|---|---|---|---|---|
| Closed storage SCIF | All SCI (including classified equipment) stored in GSA-approved containers inside the facility | Containers only | Until de-accredited | SAPF | ICS 705-1; UFC 1-11.4 |
| Open storage SCIF | SCI may be openly stored and processed without GSA containers; the room is the safe | Yes, in the open | Until de-accredited | SAPF | ICS 705-1 |
| Continuous operation | “Staffed and operated 24 hours a day, seven days a week” | Per accreditation | Until de-accredited | SAPF | ICS 705-1 |
| Secure Working Area | Discussing, handling or processing SCI “but where SCI will not be stored”; 15-min initial response | No | No time limit (DoD) | SAPWA | Tech Spec 3.I |
| Temporary SWA | SCI use “less than 40-hours per month”; accreditation “12 months or less” | No | ≤ 12 months | SAPTSWA | Tech Spec 3.J |
| Temporary SCIF | For “tactical, emergency, or immediate operational requirements” | Per approval | DoD: up to 1 year | T-SAPF | ICS 705-1; DoDM 5105.21 |
| Compartmented Area | Rooms inside a SCIF that separate compartments or programs; Types I–III (only Type III stores); no independent alarm system (2.C.4) | Type III only | With parent SCIF | SAPCA | Tech Spec 2.C |
| Vault | Storage room built to Tech Spec 3.C.5 (or FED-STD 832 for collateral) | Yes | With parent | — | Tech Spec 3.C.5 |
Table 5.2 · How the profile drives the perimeter wall and alarm response (inside the U.S.)
| SCIF profile | Perimeter wall (Tech Spec 3.C) | Initial response force (3.H) | Then |
|---|---|---|---|
| Closed storage | Wall A (standard) | 15 minutes | An SCI-indoctrinated person arrives within 60 minutes (UL 2050) or the AO-approved time 7.C.1.c |
| Secure Working Area | Wall A | 15 minutes | |
| Open storage with AO-accepted SID | Wall A | 15 minutes | |
| Open storage without SID | Wall B or Wall C (enhanced) | 5 minutes | |
| Continuous operation | Wall A | Not separately stated in 3.H. Get the AO’s determination in writing and record it on the FFC. | |
Security-in-Depth: the credit for what surrounds you
Tech Spec 2.B.1: “SID describes the factors that enhance the probability of detection before actual penetration to the SCIF occurs.” It “may alter construction requirements with AO approval” and can “extend security alarm response time to the maximum of 15 minutes.” At least one primary means is required (2.B.3):
- A military installation, embassy compound, U.S. Government compound, or contractor compound with a dedicated U.S. response force.
- A controlled building with separate building access controls, alarms and elevator controls.
- Controlled office areas adjacent to or surrounding the SCIF, protected by alarm equipment.
- A fenced compound with access-controlled vehicle and/or pedestrian gates.
SID is documented, not assumed: on FFC Section B (including external CCTV coverage maps), in the CSP’s SID block and on the Pre-Construction Checklist. SID is mandatory outside the U.S. (2.B.2) and “desired for all SCIF or SAPF” under UFC 4-010-05 1-12.
Three construction regimes
Chapter 3 covers SCIFs inside the U.S. Chapter 4 covers SCIFs outside the U.S. not under Chief of Mission authority: SID is mandatory, construction criteria follow threat Category, CSTs hold U.S. TOP SECRET clearances, and materials move under secure procurement, transport and storage. Chapter 5 covers Chief of Mission facilities, governed by ICDs and Overseas Security Policy Board standards in 12 FAH-6; the more stringent standard applies.
Category is set from the State Department’s Security Environment Threat List technical threat rating: Category I “Critical or High Technical Threat, High Vulnerability Buildings”; Category II “High Technical Threat, Low Vulnerability Buildings”; Category III “Low and Medium Technical Threat.” There is no Category IV, and open storage “is to be avoided” in Category I (and in Categories I and II under Chief of Mission).
SourcesICS 705-1·IC Tech Spec v1.5.1·DoDM 5105.21 Vol. 2·UFC 4-010-05·32 CFR 2001.43·FFC v1.5·DCSA Form 147 Guide·12 FAM 710
↑ Back to contentsChapter 06The build
Perimeter, walls & vaults
The perimeter is a sealed box: every wall, the true floor, the true ceiling, every door and window, and every duct, pipe and conduit through them. It is judged as a whole. A perfect wall with an untreated duct running through it is a failed perimeter.
What the perimeter must do
ICS 705-1 §G.1: the perimeter “shall provide a physical barrier to forced, covert and surreptitious entry,” with walls, floor and ceiling “permanently and solidly constructed and attached to each other,” providing “visual evidence of unauthorized penetration.” UFC 4-010-05 §3-3.2 adds that this “includes above the false ceilings and below raised floors.” A compliant perimeter does four jobs at once:
- Resist forced, covert and surreptitious entry (Tech Spec 3.C).
- Show visual evidence of any penetration: hard-finished, painted, inspectable surfaces.
- Contain speech to Sound Group 3 or 4 (Chapter 9).
- Provide TEMPEST/RF protection only when the CTTA recommends it (3.C.4).
True floor to true ceiling
Every perimeter wall runs from the structural slab to the underside of the deck above; a wall that stops at a suspended ceiling is not a perimeter wall. The Tech Spec wall figures require the “entire wall assembly” to be “finished and painted from true floor to true ceiling.” At the top and bottom that means:
- 16-gauge continuous top and bottom track, anchors at 32 in. on center maximum, bedded in a continuous bead of acoustical sealant.
- Remaining voids filled with fire-safe grout or acoustic sealant, including deck flutes.
- The full height finished and painted, including the portion above any drop ceiling.
Existing walls, fire ratings and RF
An existing wall of substantial material (brick, concrete, block) equal to the perimeter standard may be used with AO approval (Tech Spec 3.C.1), but it still must run slab to slab and every old sleeve must be found and treated. The Tech Spec figures are security details, not listed fire-rated assemblies; UFC 4-010-05 §3-4.1 requires fire-retardant-treated plywood in noncombustible construction and tells designers to make Tech Spec details comply with the building code.
RF protection “shall be installed at the direction of the CTTA when a SCIF utilizes electronic processing and does not provide adequate RF attenuation at the inspectable space boundary” (3.C.4), typically foil-backed wallboard or an approved radiant-barrier foil. ICS 705-1 wants it planned “during initial construction” because retrofit costs far more.
Ceilings, floors and plenums
Floors and ceilings meet “the same standards for force protection and acoustic protection as walls,” with penetrations “kept to a minimum” (Tech Spec 3.D). A drop ceiling or raised floor is a finish, not the perimeter. If an above-ceiling or raised-floor plenum connects to non-SCIF space, the true perimeter has a hole in it; the AO may require plenum motion detection or other mitigation. Motion sensors “are not normally required above false ceilings or below false floors” in the U.S. (UFC 3-4.17.3).
Utilities on perimeter walls
On walls treated for acoustics or RF, interior distribution must be “surface mounted, contained in a raceway, or an additional wall” on furring stand-offs (Tech Spec 3.G.5). UFC 4-010-05 extends that to recessed outlet boxes and panels, and prohibits recessed fire extinguisher cabinets (§3-4.4.8) and recessed PED cabinets (§3-4.7) on perimeter walls.
Windows and the 18-foot rule
“Every effort should be made to minimize or eliminate windows in the SCIF, especially on the ground floor” (3.F.1). Windows are non-opening and provide visual and acoustic protection; RF treatment follows the CTTA. Windows within 18 ft of the ground or an accessible platform must meet the perimeter standard for forced entry and be alarmed per Chapter 7 (3.F.3, 3.F.5). UFC 4-010-05 §3-4.10 specifies visual protection by acid etching, sand blasting or an obscure PVB interlayer.
Table 6.1 · Vault construction: Tech Spec 3.C.5 vs FED-STD 832
| Item | Tech Spec 3.C.5 (SCIF) | FED-STD 832 (collateral) |
|---|---|---|
| Modular | GSA-approved modular vault, AA-V-2737 | Class B = AA-V-2737 |
| Concrete | Min. 8 in reinforced; ≥ 2,500 psi; 5/8 in rebar 6 in o.c. each way, centered | Class A: 8 in reinforced; 28-day strength ≥ 3,000 psi |
| Steel-lined | 1/4 in high-yield plate, continuously welded to load-bearing members | Class C: 3/8 in plate, continuously welded |
| Door | “GSA-approved Class 5 vault door”; ABA-equipped (UFC 3-4.6.11) | Class 5 vault door (AA-D-600) |
| Day access | A vault door cannot be day-access control; build a vestibule with an access control device (Tech Spec 3.E.6) | |
SourcesICS 705-1·IC Tech Spec v1.5.1·UFC 4-010-05·FED-STD 832·AA-V-2737·Milham, ICD 705 lessons (practitioner)
↑ Back to contentsChapter 07The build
Doors, locks & containers
A SCIF door is a reinforced pedestrian door, not a vault door. During the day an access control system controls its latch; at night an FF-L-2740 combination lock throws an FF-L-2890 deadbolt and the IDS stands guard. Most door findings are hardware selection or installation errors.
Every perimeter door
- Automatic, non-hold closer on the SCIF side; hinge pins accessible from outside secured against removal (3.E.5).
- Solid: “All perimeter doors must be solid with no lites or sidelites” (UFC 3-4.6).
- Alarmed with a UL 634 Level II High Security Switch and a motion sensor (7.A.2.d, 7.A.3.a(7)).
- Acoustic performance per Chapter 9 unless a declared non-discussion area; a vestibule is recommended “to preclude visual observation and enhance acoustic protection.”
- TEMPEST requirements per CTTA guidance; life safety and accessibility per the AHJ.
Fabrication
Wood: 1-3/4 in solid core. Steel: 1-3/4 in thick with faces equal to 18-gauge minimum. Hinges reinforced to 7-gauge (cam-lift for acoustic assemblies), closer to 12-gauge, lock area predrilled or reinforced to 10-gauge (Tech Spec 3.E.6; UFC 3-4.6.1–6). DoD door assemblies are factory-tested per ASTM E90 to at least STC 50 for an STC 45 perimeter, and STC 55 for STC 50. Roll-up doors are 18-gauge steel, deadbolted on both sides inside and alarmed; double doors need the fixed leaf bolted top and bottom, an astragal and a contact on each leaf.
Table 7.1 · The three perimeter door categories (Tech Spec 3.E.1–3.E.4)
| Category | Locking hardware | Access control and alarm | How many |
|---|---|---|---|
| Primary door | FF-L-2890 pedestrian deadbolt device plus an FF-L-2740 combination lock | Approved access control device (Ch. 8); by-pass keyway allowed for ACS failure; HSS + motion | One, where visitor control happens, unless the AO approves otherwise |
| Secondary door | FF-L-2890 egress device with deadbolt; no added standalone deadbolts | ACS “must be deactivated when the SCIF is not occupied”; HSS + motion | Only with AO authorization |
| Emergency egress-only | FF-L-2890 exit-only device; no exterior hardware | Alarmed 24/7 with a local audible annunciator; no entry capability | As the building code and AHJ require |
The locks: FF-L-2740B and FF-L-2890C
FF-L-2740B electromechanical combination locks resist 20 man-hours of surreptitious entry and 30 man-minutes of covert entry, with at least 1,000,000 combinations; sales are restricted to the government and authorized contractors. Current approved models are the Kaba Mas X-10 (self-powered dial) and Sargent & Greenleaf 2740B. FF-L-2890C (22 Feb 2019) defines ten lock-extension types: primary doors use Types I–IV, rooms not regularly occupied V–VI, secondary doors VII–VIII, and exit-only doors IX–X. QPL-FF-L-2890-5 (21 Mar 2022) lists Kaba Mas CDX-10, the Lockmasters LKM10K series and the S&G 2890 series.
Electrified hardware: latch by day, deadbolt by night
ICS 705-1 approves automated access control “using at least two technologies” but not “for securing SCIF entrances when the SCIF is unoccupied.” UFC 3-4.6.5: electric strikes or electrified mortise locks “must have a positive engagement, fail secure, and approved under UL 1034 for burglar resistance.” FF-L-2890C Types II, IV, VII and VIII provide fail-secure electric release; once the combination-lock bolt is thrown it cannot be opened from outside without dialing again. Free egress stays mechanical from inside.
Containers, vault doors and the forms
In a closed storage SCIF the GSA-approved container is the storage protection. Current classes: Class 5 (10 min forced, 30 min covert, 20 hr surreptitious) and Class 6 (no forced-entry rating; 30 min covert, 20 hr surreptitious); 5-W is weapons-only and 6-S is for DoD ships. Black-label (pre-1990) containers cannot be recertified: black-label Class 1–4 cabinets became obsolete 1 Oct 2024, and Class 5 and 6 follow by 1 Oct 2028. Vault doors (AA-D-600D) use Class 5-V for national security information; the 5-A armory door and its FF-L-2937 lock are not for classified material.
Combinations change when first placed in use, when someone who knows it no longer needs access, and on possible compromise (32 CFR 2001.43(c)). SF 700 records container or door information; SF 701 is the end-of-day activity checklist; SF 702 logs every open, close and “checked by” event for the SCIF door, vaults and containers.
SourcesIC Tech Spec v1.5.1·UFC 4-010-05·FF-L-2740B·FF-L-2890C·QPL-FF-L-2890-5·DoD Lock Program: containers·NISPPAC black-label briefing·32 CFR 2001.43·ISOO forms
↑ Back to contentsChapter 08The build
Penetrations, utilities & life safety
Every duct, pipe, conduit and cable that crosses the perimeter is a potential path for sound, forced entry, covert access and, sometimes, compromising emanations. Solve each one on paper before anyone drills it, and remember that a second authority, the AHJ, has an equal say at every exit.
The general rules
- “All penetrations of perimeter walls shall be kept to a minimum” (Tech Spec 3.G.1); the same for floors and ceilings (3.D).
- Utilities serving other areas “shall not transit the SCIF unless mitigated with AO approval” (3.G.3).
- “Electrical Utilities should enter the SCIF at a single point” (3.G.4); UFC 3-4.19 adds that cabling enters “from a single location,” labeled and color-coded by classification.
- Spare conduit is allowed if “filled with acoustic fill and capped” (3.G.6).
- Seal both sides with acoustical foam or sealant “finished to match adjacent wall”; firestop where assemblies are rated (UFC 3-4.11.3).
- Metallic penetrations “may require TEMPEST countermeasures, to include dielectric breaks or grounding, when recommended by the CTTA” (3.G.2).
Ducts: the 96 square inch trigger
Vents or ducts through the perimeter that “exceed 96 square inches shall be protected with permanently affixed bars or grills,” unless “one dimension of the penetration measures less than six inches” (3.G.7). Every duct, regardless of size, still meets the SCIF’s acoustic requirement and is finished tight to the wall.
| Opening at the wall | Area | Bars or grille? |
|---|---|---|
| 12 × 10 in | 120 sq in | Yes |
| 24 × 5 in | 120 sq in | No: one side < 6 in |
| 12 × 8 in | 96 sq in | No: equals, not exceeds |
Man-bars are at least 1/2 in steel, welded vertically and horizontally 6 in on center; 3/4 in #9 expanded metal, 1-1/2 in #10 diamond mesh or 4×4 W2.9 welded wire fabric are alternatives, and permanently installed metal baffles set no more than 6 in apart may replace bars. An access port for inspecting them goes inside the perimeter, or outside with an AO-approved high-security lock.
Pipes, conduit and dielectric breaks
When the TEMPEST Countermeasures Review calls for it, UFC 4-010-05 §3-4.11.2 gives the DoD treatments: a nonconductive union on metal conduit inside the perimeter next to the penetration, or grounding within 6 in of the penetration with a No. 4 wire to the building grounding system; sprinkler and refrigerant lines grounded the same way; and a nonconductive flexible connection on a short section of duct inside the perimeter. At an RF shield the logic reverses: metal is bonded to the shield and openings become waveguides (Chapter 12).
Life safety: two authorities, no override
Every perimeter door must “comply with applicable building code, safety, accessibility standards” as the AHJ determines (3.E.5). Egress from lower-security areas “must not pass through a higher security area” (UFC 3-3.3.2). Delayed egress “is recommended with NFPA 101 compliance,” and FF-L-2890C Types III, IV, VIII and X provide fire-rated panic hardware. Egress must never depend on the access control system or its power supply.
Fire alarm and mass-notification appliances inside the SCIF are life-safety devices whose circuits also cross the perimeter. The FFC asks whether PA, music or notification systems use “fiber isolation, self-amplified speakers, other method to ensure no audio back feed,” and the IDS “shall be separate from, and independent of, fire, smoke, radon, water, and other systems” (7.A.2.h).
SourcesIC Tech Spec v1.5.1·UFC 4-010-05·FFC v1.5·FF-L-2890C·NFPA 101·ADA Standards
↑ Back to contentsChapter 09The build
Acoustics & sound masking
SCIFs where SCI is discussed “shall provide acoustic protection to prevent conversations from being inadvertently overheard outside of the SCIF” (ICS 705-1). The standard assumes an ordinary person with ordinary hearing on the other side of the wall. Deliberate technical interception is handled by TSCM, TEMPEST countermeasures and PED controls.
STC and NIC in plain English
Sound Transmission Class (STC) is a single number for how well a wall, door or window blocks airborne sound, measured in a laboratory (ASTM E90, rated per E413). Noise Isolation Class (NIC) is the similar number measured between two real rooms in the finished building (ASTM E336). The field number includes every flanking path: over the wall, under the door, through ducts and electrical boxes. The lab number describes the product; the field number describes what you built.
Sound Group 3 and Sound Group 4
Sound Group 3 (STC 45 or better; field NIC 40): “Loud speech from within the SCIF can be faintly heard but not understood outside the SCIF. Normal speech is unintelligible with the unaided human ear.” It is the default perimeter. Sound Group 4 (STC 50 or better; field NIC 45): “Very loud sounds … such as loud singing, brass music, or a radio at full volume, can be heard with the human ear faintly or not at all outside the SCIF.” Rooms with amplified audio such as VTC “must meet Sound Group 4” (UFC 3-4.3.2).
Build it so the field number holds
- Walls true floor to true ceiling; track bedded in sealant; deck flutes filled (Tech Spec wall figures; UFC 3-4.4).
- Insulation “fastened to prevent sliding”; board joints staggered; gaps sealed both sides “with a non-hardening caulk” (UFC 3-4.4.5).
- For STC 50, four layers of 5/8 in GWB (two each side), or factory-laminated GWB meeting ASTM C1766 (UFC 3-4.4.2–3).
- No recessed or back-to-back boxes on perimeter walls (Tech Spec 3.G.5).
- Tested door assemblies with cam-lift hinges; silencers or Z-ducts on every duct and return (UFC 3-4.6.1, 3-4.13).
Testing at accreditation
“With all SCIF doors closed, all perimeter walls and openings … shall be tested along multiple points” to confirm the Sound Group (Tech Spec Ch. 9, as quoted by practitioner sources). Audio (non-instrumental) tests “must be approved by the AO”; instrumental tests are performed only by those trained in audio testing, with results of NIC 40 (Group 3) or NIC 45 (Group 4). The quoted setup places the speaker 6 ft from the wall and 4 ft above the floor, at “loud” or “very loud” speech.
Mitigations and sound masking
When construction cannot reach the Sound Group at a specific weak point, the Tech Spec allows AO-approved structural enhancement, stand-off distance or sound masking. Masking rules (Ch. 9.E, as quoted): transducers “placed close to, or mounted on” the leakage paths; volume set by listening outside until conversations are unintelligible; generators “permanently installed,” with no AM/FM receiver, located within the SCIF; any recording capability disabled; wiring within the perimeter to the greatest extent possible. Masking systems are subject to TSCM evaluation.
SourcesICS 705-1·UFC 4-010-05·ASTM E90·ASTM E413·ASTM E336·K.L. Security (quotes Ch. 9)·Speech masking: ICD 705 (quotes Ch. 9)·PSC (practitioner)
↑ Back to contentsChapter 10The build
Intrusion detection & UL 2050 / Extent 3
The IDS guards a SCIF when nobody is inside. It must detect entry at every door and along every path to the material, report at once over a protected line to a qualified station, and bring a response force fast enough that nothing is compromised. ICS 705-1: installation, components and monitoring stations “shall comply with Underwriters Laboratories (UL) 2050 Extent 3 standards.”
Table 10.1 · The 12 numbers every SCIF IDS installer should know (Tech Spec Ch. 7 as quoted from the public v1.4-era copy; confirm against v1.5.1; some values allow AO-approved alternatives)
| # | Requirement | Value | Cite |
|---|---|---|---|
| 1 | UL installation level | UL 2050 Extent 3 | 7.A.2.b |
| 2 | Perimeter door switch | UL 634 listed High Security Switch, Level II (new accreditations) | 7.A.2.d |
| 3 | Motion sensors | UL 639 listed; HSS and motion on every perimeter door | 7.A.2.d; 7.A.3.a(7) |
| 4 | Entry delay at the primary door | ≤ 30 seconds | 7.A.3.a(6) |
| 5 | Backup power | 24 hours uninterruptible | 7.B.5 |
| 6 | False alarms | ≤ 1 per 30 days per IDS partition | 7.A.2.p |
| 7 | Response force, closed storage | 15 minutes | 3.H(a) |
| 8 | Response force, open storage | 15 minutes with Security-in-Depth; 5 minutes without | 3.H(b); 32 CFR 2001.43 |
| 9 | SCI-indoctrinated person on site | 60 minutes (UL 2050) or the AO-approved time | 7.C.1.c |
| 10 | Service start after a trouble signal | Within 4 hours | 7.C.2 |
| 11 | Recurring IDS test | Semiannual | 7.D.3 |
| 12 | Motion walk-test pass | Alarm on 3 of every 4 consecutive four-step trials | 7.D.3 |
What Extent 3 actually means
“Extent of protection” is UL’s term for “the amount of alarm protection installed to protect a particular area, room or container” (UL CS-ASD-NISS instructions). Tech Spec 7.A.2.b: “Installation shall comply with an Extent 3 installation as referenced in UL 2050.” Extent 5 is a reduced, patrol-based level that needs CSA approval under 32 CFR 117.15(d)(4); the Tech Spec offers no Extent 5 option, so it never applies to a SCIF or SAPF. Systems built and used by the U.S. Government need no UL certificate but must still meet Extent 3 installation requirements (7.A.2.c).
Sensors, panel and modes
- Sensors inside the SCIF; failed sensors cause “immediate and continuous alarm activation”; dual-technology sensors only if each technology reports independently.
- The PCU is inside the SCIF, and “only SCIF personnel may initiate changes in access modes” (7.A.3.b(1)); it displays which sensor tripped, holds alarms until cleared locally (auto-reset disabled), and signals power changes locally and at the station.
- Cabling that leaves the SCIF uses encrypted line security or ferrous conduit with permanently sealed joints (no set screws), with junction boxes on GSA-approved locks (7.A.2.e).
- Independent of fire, smoke, radon and water systems (7.A.2.h); no audio or video capability without AO approval (7.A.2.l).
- Modes: only SCI-indoctrinated people arm or disarm; who armed and disarmed is recorded; tamper and emergency-exit circuits stay armed in disarmed mode; failures to arm or disarm are reported and kept two years.
UL 2050 certifies a company, not a product
The CRZH-listed alarm service company completes UL Form CS-ASD-NISS for each protected area, installs and tests, and issues the National Industrial Security System certificate. Contractor SCIFs “shall maintain a current UL certificate of installation and service,” renewed after any IDS change. The current edition is UL 2050 Edition 6 (7 Apr 2025); much public UL guidance was written under Edition 5.
| Check on the certificate | What to confirm |
|---|---|
| File number and CCN | Matches the UL Product iQ listing: CRZH (company); CRZM only if a NIMS monitors; not mercantile CVSG |
| Dates | Current; renewed after any IDS change |
| Each system | Extent 3, monitoring location, line security encrypted |
| Response time | Matches the AO/CSA approval, the FFC and the response agreement |
Encryption and the FIPS 140-2 sunset
Transmission to the station uses FIPS-certified encryption: a UL 1610 PCU needs FIPS 197 (AES) or FIPS 140-2; a UL 1076 PCU needs FIPS 140-2 (7.A.3.b(10)). NIST’s CMVP moves FIPS 140-2 validations to the Historical List on 21 September 2026; NIST says historical modules remain supported “for existing systems.”
Acceptance testing: what it should prove
- Every motion sensor passes the walk test: four steps at one step per second, about 30 in each, alarm on at least 3 of 4 trials.
- Every HSS alarms before the non-hinged side opens farther than the door’s thickness, emergency exits included.
- Every equipment cover trips tamper in both modes.
- Intrusion, failed-sensor, tamper, maintenance and shunt events annunciate at the PCU and the station.
- Backup transfer without alarm; entry delay ≤ 30 s; defaults changed; encryption end to end.
SourcesICS 705-1·IC Tech Spec v1.5.1·UL CS-ASD-NISS instructions·UL NISS certification·UL 2050 Ed. 6·32 CFR 117.15·DCSA SAP Checklist (Jan 2026)·NIST FIPS 140-3 transition·UFC 4-010-05
↑ Back to contentsChapter 11The build
Access control & identity
Card readers control who walks in during the workday. They never lock up an empty SCIF. When the last person leaves, the FF-L-2740 combination lock and the armed IDS take over. Everything about an access control design follows from that division of labor.
Two technologies at the door
ICS 705-1 §G.2.b approves “automated access control systems using at least two technologies (badge, PIN, biometric, etc.),” electromechanical or mechanical devices, and personal recognition in small facilities or at a single monitored entrance, and states these methods are not approved for securing SCIF entrances when the SCIF is unoccupied. UFC 3-4.17.1: “At a minimum, provide card reader with keypad at the primary entrance and when provided, the secondary entrance,” with the CAC as the default DoD credential. If ACS and IDS are integrated, ACS notifications rank below IDS alarms (Tech Spec 7.A.2.i).
Where the head-end lives, and how its lines are protected
The Fixed Facility Checklist asks: “Is automated access control system located within a SCIF or an alarmed area controlled at the SECRET level?” It also asks whether transmission lines are “protected by 128-bit encryption/FIPS 140,” whether external devices have tamper protection, and whether “ID data and PINs [are] restricted to SCI-indoctrinated personnel.” A campus server or cloud head-end in unsecured space does not meet this without an AO-approved architecture, and routine remote support by uncleared vendor technicians is ruled out.
Secondary doors go dark when the SCIF closes
Tech Spec 3.E.3: the secondary-door ACS “must be deactivated when the SCIF is not occupied.” Tie deactivation to the closing procedure (for example the IDS arming sequence), not to a clock schedule that drifts and breaks on holidays, and demonstrate the disabled state at acceptance.
Table 11.1 · Who controls each door, by SCIF state
| State | Primary door | Secondary door | Egress-only door | IDS |
|---|---|---|---|---|
| Occupied | ACS with ≥ 2 technologies, or personal recognition at a monitored single entrance; visitor control here | ACS active, if the AO authorized the door | Alarmed 24/7; exit only | Disarmed; tamper and emergency-exit circuits stay armed |
| Closing | Last person clears the space, locks the FF-L-2740 (throwing the 2890 deadbolt), arms the IDS | ACS deactivated | Alarmed | Armed; record of who armed |
| Unoccupied | FF-L-2740 lock and IDS only | Secured by its 2890 deadbolt | Alarmed | Armed (secure mode) |
| Opening | Authorized person dials in and disarms from inside within the entry delay (≤ 30 s) | Reactivate per SOP | Alarmed | Disarmed; record of who disarmed |
PIV, CAC and the federal identity stack
FIPS 201-3 (January 2022) is the current PIV standard; NIST SP 800-116 Rev. 1 maps security areas to factors: Controlled (1, e.g. PKI-CAK), Limited (2, PKI-AUTH + PIN) and Exclusion (3, adding a biometric). A PIV or CAC card plus PIN fits the two-technology rule naturally; a proximity card alone, or a keypad alone, does not. Agencies buy PACS from GSA’s FIPS 201 Approved Products List, where readers are approved only as part of a tested topology.
Platforms, including Hirsch
Integrators often inherit or price against an enterprise platform: Hirsch Velocity, LenelS2 OnGuard, Software House C•CURE 9000, AMAG Symmetry, Genetec Synergis or Gallagher Command Centre, among others. Hirsch (Hirsch Group, formerly Vitaprotech; previously part of Identiv) describes itself as a long-time provider of high-security access control to the U.S. federal government. Per its own datasheets: Velocity 3.9 is the current software release; Mx controllers are UL 294 and UL 1076 listed and use FIPS 140-3 certified cryptography; integrated Mx controllers support two-person rule, occupancy counting, door interlocking (each interlock needs AHJ approval and must not block egress) and anti-passback; and TS ScramblePad readers reorder their keypad digits on each use. Those are manufacturer claims, not AO approvals, and CMVP certificate numbers should be obtained and verified.
SourcesICS 705-1·IC Tech Spec v1.5.1·FFC v1.5·UFC 4-010-05·NIST SP 800-116 Rev. 1·IDManagement: FIPS 201·Hirsch Mx datasheet·Hirsch Velocity datasheet·TS ScramblePad datasheet·Identiv sale completed
↑ Back to contentsChapter 12The build
RED/BLACK, EMI filters & shield penetrations
RED is anything carrying classified information in the clear. BLACK is everything carrying only encrypted or unclassified information: building power, phones, the unclassified LAN, fire alarm, IDS, access control, CCTV. RED/BLACK discipline keeps RED signals from leaking onto anything BLACK that leaves the room, and the CTTA, not the build team, decides which countermeasures a facility needs.
Who decides
The Certified TEMPEST Technical Authority reviews plans “to determine if TEMPEST countermeasures are required and recommend solutions” (Tech Spec 3.A.3). UFC 4-010-05 calls the output the TEMPEST Countermeasures Review (TCR), requested through the TEMPEST addendum during planning. The public construction documents state when the CTTA’s direction applies (walls 3.C.3–3.C.4, doors 3.E.5, metallic penetrations 3.G.2, single-point entry 3.G.4) but never list filter ratings or separation distances.
The controlling TEMPEST issuances are named here for orientation only: CNSSP No. 300 (national policy), CNSSI No. 7000 (TEMPEST Countermeasures for Facilities, which defines inspectable space), CNSSAM TEMPEST/1-13 (RED/BLACK Installation Guidance) and CNSSI No. 7003 (Protected Distribution Systems). Their technical content is not public and is not reproduced.
Inspectable space and why many SCIFs aren’t shielded
Inspectable space is the three-dimensional zone around classified equipment that the government can see into and control; the CTTA determines it. RF protection is installed “at the direction of the CTTA when a SCIF utilizes electronic processing and does not provide adequate RF attenuation at the inspectable space boundary” (3.C.4). Outside the U.S. and not under Chief of Mission authority, “TEMPEST countermeasures shall be pre-engineered into the construction” (4.H.1). An unshielded SCIF still depends on basics: label RED and BLACK, never share trays, bundles or patch panels, use fiber where called for, and add no metallic penetrations.
What a power filter does
A power-line filter is a passive low-pass network of inductors and capacitors: 60 Hz passes, RF is blocked and shunted to the metal case, and from there to whatever low-impedance return the case is bonded to — at a shielded room, the shield itself. MIL-HDBK-232A §4.5 (1987, historical) puts the requirement on the return path: it must carry the current and “present minimal impedance to ground to the shunted current at all frequencies of interest.” Where there is no shield, the return is the enclosure and facility ground the design provides, and the CTTA sets the detail. It is rated by insertion loss in dB across a frequency range, bench-tested per MIL-STD-220 with 50-ohm source and load; installed impedances differ, which is why the finished room is tested. Vendor datasheets commonly publish “100 dB class” figures; the level your project needs comes from the CTTA, shield designer and specification, not a catalog.
Mounting, safety and power quality
- Bond the case metal-to-metal on paint-free surfaces; a long round “ground wire” is not an RF bond. Keep input and output wiring physically apart.
- Stored charge: filter capacitors hold charge after the breaker opens. Lock out and tag out, wait the labeled discharge time, verify zero with a rated meter, apply a shorting stick, then open the compartment.
- Leakage: line-to-case capacitors leak small currents that add across filters and phases; that current can nuisance-trip a GFCI upstream of a filter. GFCI placement is an engineer-of-record and AHJ decision. Never lift grounds.
- kVAR: high-capacitance filters can overload a generator, destabilize voltage or prevent startup. Include filter kVAR in generator and UPS sizing and test transfer with filters energized.
Every other conductor and opening
Low-speed signal lines (phone, fire alarm loops, door contacts, readers) get signal-line filters at the penetration panel. High-speed data goes through the shield on all-dielectric fiber in a waveguide, with converters on filtered power; no PoE or copper Ethernet through the wall. At a shield, metal pipe, conduit and tray are welded or bonded and openings are sized as waveguides-beyond-cutoff; ducts get bonded honeycomb vents. At a non-shielded perimeter the logic reverses to a dielectric break or grounding, only where the CTTA directs. Never pass any conductor through a waveguide: a wire in a tube makes a coaxial line with no cutoff.
SourcesIC Tech Spec v1.5.1·ICS 705-1·UFC 4-010-05·NIST glossary: TEMPEST·Genisco: how filters work·Premier: installation practices·ETS-Lindgren filter manual·Premier: filters & generators·2-95 (historical mirror)
↑ Back to contentsChapter 13The build
PEDs, telecom & CCTV
Anything that can record, transmit or observe is a risk inside a SCIF: phones, watches, speakers, cameras, wireless locks and building controls. ICS 705-1 says PEDs “pose a risk to SCI,” and RF transmitters may not be introduced unless a competent authority such as the CTTA evaluates them as low risk and the AO approves.
Portable electronic devices
Tech Spec Chapter 10 covers PEDs with recording capabilities and embedded technologies: approved use, prohibitions, risk levels and mitigation. As summarized from a public edition, low-risk devices have no recording or transmitting capability, medium-risk devices have features that “can be physically disabled,” and high-risk devices need “more extensive or technically complex mitigation”; personally owned devices are prohibited from processing SCI, and medical devices go through separate review. A 30 June 2023 Secretary of Defense memo directed DoD components to program electronic device detection systems and mitigation in all DoD SCIFs and SAPFs by 30 September 2024.
PED lockers sit outside the primary entrance, are never recessed into the perimeter wall, and cannot be within 10 ft of equipment processing unencrypted national security information (UFC 3-4.7).
Detection technology: what each can and cannot see
| Category | Detects | Misses |
|---|---|---|
| Passive RF sensor network (WIDS) | Transmitting cellular, Wi-Fi, Bluetooth/BLE; locates emitters | Powered-off or silent devices; sensors are equipment inside the SCIF needing AO/CTTA review |
| Fixed RF detector at the vestibule | Cellular and often Wi-Fi/BT in a set radius | Can’t identify the device; nuisance alarms from outside RF |
| Handheld RF / direction finder | Sweeps and localizes | Operator-dependent; standby phones transmit rarely |
| Ferromagnetic or metal screening | Ferrous or metallic objects, powered or not | Not phone-specific; throughput and false alarms |
Telecommunications
Tech Spec Chapter 11 covers unclassified telephones and information systems, CCTV at entry points, wireless, environmental infrastructure, emergency notification, system access, cable control and Protected Distribution Systems. Practical rules for the build team:
- Phones: NCSC’s Telephone Security Group publishes an approved endpoints list for SCIF use; the FFC asks whether speakerphones and microphones are disabled or AO-approved, and whether remote room monitoring is disabled.
- Telecom rooms with encryption equipment go “within or adjacent (shared wall) to the secure area” to minimize PDS (UFC 3-3.3.2).
- PDS (CNSSI 7003) protects unencrypted classified lines crossing lesser areas; “Avoid the use of PDS whenever possible” (UFC 3-4.20). Most IDS and ACS cabling is not PDS.
- Cabling enters at a single location, labeled and color-coded by classification (UFC 3-4.19).
- Wireless anything (locks, readers, sensors, cellular communicators, building-automation radios) needs CTTA evaluation and AO approval. Design wired first.
CCTV at the entrance, never inside
UFC 3-4.17.2: “Cameras are not allowed within the perimeter or enable observation within the perimeter.” An exterior camera at the primary entrance is permitted for remote control of the door from inside, and a video intercom may provide this. Tech Spec Chapters 8.E and 11.D treat CCTV as a supplement to entry control, never a substitute for the lock, the ACS or the IDS.
| Do | Don’t |
|---|---|
| Frame faces and the door approach | Capture keypad PINs, the combination dial, badge data or a view through the open door |
| Keep monitors and release controls inside, run by SCI-indoctrinated staff | Put IP cameras, doorbells or intercoms with microphones inside the perimeter |
| Use cameras without audio near SCIF walls | Run camera cable through the SCIF to reach the other side of the building |
| Map corridor coverage on FFC Section B for SID credit | Present CCTV as a reason to relax the lock, ACS or IDS |
SourcesICS 705-1·IC Tech Spec v1.5.1·SECDEF memo, 30 Jun 2023·UFC 4-010-05·DCSA SAP Checklist (Jan 2026)·NCSC TSG approved endpoints·NIST glossary: PDS·Apple: Airplane Mode·I Dig Hardware: interlocks
↑ Back to contentsChapter 14The build
Construction security & build sequence
A SCIF tenant improvement follows the normal design-bid-build path with security gates in front of every big commitment: designing, signing the contract, closing the walls and moving in. The controls exist so the AO can trust work it will never see.
Table 14.1 · Phase 0–5 build sequence with security gates (planning aid; the AO-approved CSP and design govern)
| Phase | Key outputs | GC and integrator focus | Security gate |
|---|---|---|---|
| 0 · Sponsorship & due diligence | Sponsor and AO identified; SSM appointed; site feasibility | Walk above ceilings and below floors; map slab cores, deck flutes, shared utilities, monitoring path | “Security begins when the initial requirement for a SCIF is known” (Tech Spec 2.A) |
| 1 · Planning & pre-design | Concept approval; preliminary CSP; FFC; TEMPEST addendum | Price CSP site controls; confirm response time and monitoring | AO and CTTA engaged before design is final |
| 2 · Design | Wall types, door and penetration schedules, IDS/ACS design, AHJ life-safety review | Security notes on the trade sheets; no TBDs on hardware, penetrations or IDS layout | AO approves design concept, CSP and final design (3.A) |
| 3 · Procurement & award | Award; citizenship flow-down; long-lead orders | FF-L-2890/2740 from the QPL; tested STC assemblies; UL 2050 company | No award without an approved CSP (3.B.1) |
| 4 · Construction | Site controls; inspections; photo record; change log | Pre-cover hold point; every field change through the SSM | Violations or deviations to the AO within 3 business days (3.A) |
| 5 · Test & accredit | Acoustic, IDS, UL 2050 certificate, TEMPEST/RF and TSCM as required; as-builts; final FFC | Deliver test reports, certificates and turnover binder | AO inspection and accreditation; no SCI before the letter |
The Construction Security Plan
“Prior to awarding a construction contract, a CSP for each project shall be developed by the SSM and approved by the AO” (Tech Spec 3.B.1). It documents project identity and adjacencies, Security-in-Depth, control of plans and documents, protection of IDS technical documentation, workforce vetting and badging, escorts and CSTs, site access controls, material procurement and storage, the inspection schedule with hold points, violation reporting, and renovation barriers that segregate workers from operational areas.
Who may design, build and install
- Design: U.S. companies using U.S. citizens or U.S. persons (UFC 1-17).
- Construction: “should be performed by U.S. companies using U.S. citizens … but may be performed by U.S. companies using U.S. persons,” with AO-ensured mitigations (3.B.5).
- IDS installation and testing: “U.S. companies using U.S. citizens” (7.D.1; UFC 1-18.1). U.S. person status does not satisfy this.
Citizenship, U.S. person status and clearance are separate tests. Flow the requirements to every subcontractor.
Site controls and materials
Tech Spec 3.B.6 lists identity verification, random searches at entry and exit, prohibited-item signage, physical barriers and vehicle inspections; “the AO may impose procedures for the procurement, shipping, selection, and secure storage of construction materials” (UFC 4-3). Overseas, controls scale with threat Category: CST start points, cleared finish workers, secure transport and secure storage areas.
SourcesIC Tech Spec v1.5.1·UFC 4-010-05·CSP form v1.5·ICS 705-2·PSC: crafting a CSP (practitioner)·SAME 2026 (practitioner)·CenCore Q&A (practitioner)
↑ Back to contentsChapter 15Reference
Top traps
The mistakes that recur across SCIF projects are rarely exotic. They are basic details done out of sequence, left unfinished or never documented. Items in the first group are schedule problems no amount of field effort fixes; most of the rest are cheapest to catch at the pre-cover inspection.
| Trap | Why it fails | Do this instead |
|---|---|---|
| Authority, paperwork & sequence | ||
| Engaging the AO after design, material orders or contracts | Tech Spec 2.A requires coordination first; late findings force redesign | Identify the AO at kickoff; submit concept, preliminary CSP and TEMPEST addendum in planning |
| Awarding the contract or starting demo before the CSP is approved | Violates Tech Spec 3.B.1; workers enter before site controls exist | Treat CSP approval as the award gate |
| Calling a product “ICD 705 certified,” “TEMPEST compliant” or “UL 2050 listed” | The AO accredits facilities; the CTTA recommends countermeasures; UL 2050 certifies the alarm company | Use verifiable listings and “subject to AO/CSA approval” wording |
| Exceeding a standard “to be safe” | Needs a waiver and costs mandatory reciprocity (Tech Spec 2.A; ICS 705-1) | Discuss enhancements with the AO before they reach the drawings |
| Assuming Security-in-Depth, or letting it lapse | Without accepted SID, open storage needs Wall B/C and a 5-minute response | Get the SID determination in writing; put SID systems under change control |
| Sending drawings, checklists or TEMPEST findings through open channels | Location + “SCIF” is CUI; TEMPEST findings at a location are at least CONFIDENTIAL | Secure file transfer set up before design; handle per the CSP |
| Perimeter, doors & penetrations | ||
| Walls stop at the drop ceiling or leave deck flutes open | Not true floor to true ceiling; acoustic and visual-evidence failure | Detail flute infill before bid; photograph every top-of-wall segment |
| Recessed or back-to-back boxes and cabinets on perimeter walls | Tech Spec 3.G.5; UFC 3-4.4.7–8; direct flanking path | Surface raceway or furred wall; note it on the trade sheets |
| Ducts over 96 sq in without bars, baffles or access ports | Tech Spec 3.G.7; IDS is not listed as a substitute | Mechanical engineer lists every perimeter duct opening and treatment |
| Other tenants’ utilities routed through the SCIF; scattered entries | Tech Spec 3.G.3–3.G.4 | One planned utility entry; reroute mains in design |
| Non-QPL locks, fail-safe strikes or maglocks; exterior hardware on egress-only doors | Tech Spec 3.E; UFC 3-4.6.5; FF-L-2890C | Door schedule lists FF-L-2890 type, UL 1034 strike and HSS per door |
| “STC door” assembled from mixed parts; racked frames | Only tested assemblies carry the rating; binding bolts and seal gaps | Specify the tested assembly; set frames plumb, level, square |
| Acoustics, IDS & access control | ||
| VTC or speakerphone added to a Sound Group 3 room | Amplified audio requires Sound Group 4 (UFC 3-4.3.2) | Get the AV plan in design; zone rooms before walls are detailed |
| Perimeter door with HSS but no motion (or motion but a standard contact) | Tech Spec 7.A.3.a(7) requires both; Level II for new accreditations | Door and sensor schedule reviewed against the 12 numbers (Table 10.1) |
| PCU or keypad outside the SCIF; set-screw conduit; unlocked junction boxes | Tech Spec 7.A.3.b(1), 7.A.2.e | PCU and arming stations inside; encrypted lines or sealed ferrous conduit |
| Batteries short of 24 h; communicator left off the calculation | Tech Spec 7.B.5; the alarm never reaches the station | Measured-current calculation including every device in the alarm path |
| Mercantile certificate, expired certificate, or not renewed after changes | ICS 705-1 requires a current UL 2050 certificate | Verify CRZH listing and certificate fields; track the expiration date |
| ACS head-end in the cloud or an unsecured server room; unencrypted reader runs | FFC §C.1: SCIF or SECRET-controlled alarmed area; FIPS-protected lines | AO-approved architecture before bid |
| TEMPEST, shielding & operations | ||
| Filters reversed, shared boxes, painted bonds; copper through a waveguide | RF bypasses the filter; a wire in a tube has no cutoff | Unfiltered conductors stop outside, filtered conductors continue in (a rule about conductors, not boxes); all-dielectric fiber only; see the Field Guide |
| A penetration added after the shield test | The test describes a room that no longer exists | Freeze the penetration schedule; review and retest every change |
| Moving SCI, furniture or people in before the letter | SCI before accreditation is a violation (DoDM 5105.21 Vol. 2) | Treat the letter as Gate C |
Chapter 16Reference
Glossary of 60 key terms
Plain definitions of the terms that appear most often in SCIF and SAPF submittals, with the chapter where each is explained. Where one abbreviation means two things, both are given.
A – C
D – F
G – N
O – S
T – W
Chapter 17Reference
Reference library
Official public sources behind this primer, checked September 2026. Many www.dni.gov links now redirect to archive.dni.gov; where available, the stable DoD Lock Program (NAVFAC EXWC) mirror is listed. Confirm the current version with the issuer before you cite it in a specification.
| Document | Issuer | Version / date | Link |
|---|---|---|---|
| Intelligence Community (ODNI / NCSC) | |||
| ICD 705, SCI Facilities | ODNI | 26 May 2010 | archive.dni.gov/…/ICD/ICD-705-SCIFs.pdf |
| ICS 705-1, Physical & Technical Security | ODNI / NCSC | 17 Sep 2010 | exwc.navfac.navy.mil/…/DoD_Locks/PDFs/ICS-705-1.pdf |
| ICS 705-2, Accreditation & Reciprocal Use | ODNI / NCSC | 22 Dec 2016 | exwc.navfac.navy.mil/…/DoD_Locks/PDFs/ICS-705-2.pdf |
| IC Tech Spec for ICD/ICS 705 | NCSC | v1.5.1, 26 Jul 2021 | exwc.navfac.navy.mil/…/ICD-ICS-705_Tech_Spec.pdf |
| SCIF Fixed Facility Checklist v1.5 (form) | NCSC | v1.5 forms | archive.dni.gov/…/SCIF-Fixed-Facility-Checklist-V15.pdf |
| TSG approved telephone endpoints list | NCSC TSG | May 2026 | archive.dni.gov/…/May_2026_TSG_AEL_Endpoints.pdf |
| Department of Defense | |||
| DoDM 5105.21 Vol. 2, SCI Admin Security Manual | USD(I&S) | 2012; Change 2, 2020 | esd.whs.mil/…/dodm/510521m_vol2.pdf |
| DoDM 5205.07, SAP Security Manual | USD(I&S) | 17 Jan 2025 | esd.whs.mil/…/dodm/520507m1.PDF |
| UFC 4-010-05, SCIF/SAPF Design & Construction | DoD (WBDG) | 26 May 2023 | wbdg.org/FFC/DOD/UFC/ufc_4_010_05_2023.pdf |
| DoD Lock Program · (800) 290-7607 | NAVFAC EXWC | Current | exwc.navfac.navy.mil/DoD-Lock-Program/ |
| FF-L-2740B combination locks | GSA | 15 Jun 2011 | exwc.navfac.navy.mil/…/DoD_Locks/PDFs/FF-L-2740.pdf |
| FF-L-2890C lock extensions; QPL | GSA | 2019; QPL 2022 | exwc.navfac.navy.mil/…/DoD_Locks/PDFs/FF-L-2890C.pdf |
| NISPOM, DCSA and CDSE | |||
| 32 CFR 117.15, NISPOM safeguarding | DoD / eCFR | Current eCFR | ecfr.gov/current/title-32/…/section-117.15 |
| 32 CFR 2001.43, Storage (supplemental controls) | ISOO / eCFR | Current eCFR | ecfr.gov/current/title-32/…/section-2001.43 |
| DoW SAP Security Compliance Checklist | DCSA | Jan 2026, v2 | dcsa.mil/…/SAP Security Compliance Checklist (2026) |
| CDSE SA501, ICD 705 construction for SAP | CDSE | eLearning | cdse.edu/Training/eLearning/SA501/ |
| UL, identity and cryptography | |||
| UL 2050 NISS certification (CRZH / CRZM) | UL Solutions | Ed. 6, 7 Apr 2025 | ul.com/services/national-industrial-security-… |
| FIPS 201 Approved Products List | GSA | Current | idmanagement.gov/buy/ |
| NIST SP 800-116 Rev. 1 (PIV for PACS) | NIST | 29 Jun 2018 | nist.gov/…/sp-800-116-revision-1-guidelines-use-piv |
| FIPS 140-3 transition (CMVP) | NIST | 140-2 sunset 21 Sep 2026 | csrc.nist.gov/projects/fips-140-3-transition-effort |
| State Department, life safety and accessibility | |||
| 12 FAM 710 (Chief of Mission SCIFs) | State Dept. | Current FAM | fam.state.gov/fam/12fam/12fam0710.html |
| NFPA 101 Life Safety Code | NFPA | Edition per AHJ | nfpa.org/…/nfpa-101-standard-development/101 |
| Historical (context only, never current requirements) | |||
| NSA, “TEMPEST: A Signal Problem” | NSA | Declassified article | nsa.gov/portals/75/…/cryptologic-spectrum/tempest.pdf |
| IC Tech Spec v1.5 | NCSC | 2020; superseded | archive.dni.gov/…/IC-Tech-Specs-…-SCIFs-v15.pdf |